8020 S STEWART AVE 90045

Certificate Information: 8020 S STEWART AVE 90045

Application / Permit
23014-20000-03689
Plan Check / Job No.
B23VN12333
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Second floor addition to existing garage and conversion to 2-story Accessory Dwelling Unit per LAMC 12.22 A.33 (c)-(d) with an attached deck
Permit Issued
Issued on 12/18/2023
Issuing Office
Valley
Current Status
CofO Issued on 6/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2023 APPLICANT
Assigned to Plan Check Engineer 9/14/2023 VAHAN JIVALAGIAN
Corrections Issued 9/19/2023 VAHAN JIVALAGIAN
Quality Review Completed 9/20/2023 OMID HEDAYAT
Building Plans Picked Up 9/22/2023 APPLICANT
Applicant returned to address corrections 12/14/2023 VAHAN JIVALAGIAN
Plan Check Approved 12/18/2023 VAHAN JIVALAGIAN
Issued 12/18/2023 APPLICANT
CofO in Progress 5/29/2024 BOBBY KEY
Permit Finaled 6/4/2024 DANIEL ORRANTE
CofO Issued 6/4/2024 DANIEL ORRANTE
Permit Finaled 6/4/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/29/2023 BRENDEN HAWK
Eng Process Fee Ord 176,300 Cleared 10/2/2023 BRENDEN HAWK
Sewer availability Cleared 10/2/2023 BRENDEN HAWK
Specific Plan Cleared 10/16/2023 FREDDY GARCIA
Low Impact Development (LID) Cleared 11/16/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 11/28/2023 BRENDEN HAWK
Construction near power lines Cleared 12/6/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Amador,, Carlos; Lic. No.: L9365 5445 DEL AMO BLVD #202      LAKEWOOD, CA 90712
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/3/2024 Approved BOBBY KEY
PLUMBING-Rough 1/3/2024 Partial Approval BOBBY KEY
ELECTRICAL-Rough 1/30/2024 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/30/2024 Partial Approval BOBBY KEY
Sewer 1/30/2024 Approved BOBBY KEY
BUILDING-Rough-Frame 2/15/2024 Approved BOBBY KEY
ELECTRICAL-Rough 2/15/2024 Approved BOBBY KEY
Green Building Rough 2/15/2024 Approved BOBBY KEY
HVAC-Rough 2/15/2024 Approved BOBBY KEY
Interior/Exterior Lathing 2/15/2024 Partial Approval BOBBY KEY
PLUMBING-Rough 2/15/2024 Conditional Approval BOBBY KEY
PLUMBING-Rough 2/16/2024 Approved BOBBY KEY
Underground Mechanical 2/16/2024 Partial Approval BOBBY KEY
Insulation 2/21/2024 Approved BOBBY KEY
Interior/Exterior Lathing 2/21/2024 Approved BOBBY KEY
Shower Pan 2/21/2024 Approved BOBBY KEY
Drywall Nailing 2/26/2024 Approved BOBBY KEY
ELECTRICAL-Final 4/19/2024 Approved TEMISTOCLES CAAL
Final 4/19/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Final 4/19/2024 Approved TEMISTOCLES CAAL
HVAC-Final 4/19/2024 Approved TEMISTOCLES CAAL
PLUMBING-Final 4/19/2024 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 4/19/2024 SGSOV Not Required TEMISTOCLES CAAL
Smoke Detectors 4/19/2024 Approved TEMISTOCLES CAAL
Service/Power Release 4/25/2024 Approved TEMISTOCLES CAAL
Final 5/29/2024 OK to Issue CofO BOBBY KEY