5846 N WILLIS AVE 91411
Certificate Information: 5846 N WILLIS AVE 91411
- Application / Permit
- 23014-20000-03679
- Plan Check / Job No.
- B23VN12311
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 17'-8" X 20'-2" ADDITION TO SFD FOR NEW BEDROOM AND BATHROOM
- Permit Issued
- Issued on 9/26/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 9/16/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 9/20/2023 | APPLICANT |
| Plan Check Approved | 9/26/2023 | ALEC MOUSAKHANIAN |
| Issued | 9/26/2023 | APPLICANT |
| CofO in Progress | 6/3/2024 | RYAN SALAZAR |
| Permit Finaled | 11/22/2024 | RUBEN SALAS |
| CofO Issued | 11/22/2024 | RUBEN SALAS |
| Permit Finaled | 11/22/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2023 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 9/22/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 9/22/2023 | TAL SHEMEN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/12/2024 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 1/16/2024 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 1/16/2024 | Approved | RYAN SALAZAR |
| Insulation | 1/30/2024 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 1/30/2024 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 3/20/2024 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Rough | 3/20/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/20/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/27/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 3/27/2024 | Approved | RYAN SALAZAR |
| Insulation | 3/27/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/27/2024 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 4/8/2024 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 4/8/2024 | Partial Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 5/30/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 5/30/2024 | Approved | RYAN SALAZAR |
| Final | 5/30/2024 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 5/30/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 5/30/2024 | Approved | RYAN SALAZAR |
| HVAC-Final | 5/30/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 5/30/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 5/30/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 5/30/2024 | Approved | RYAN SALAZAR |