5846 N WILLIS AVE 91411

Certificate Information: 5846 N WILLIS AVE 91411

Application / Permit
23014-20000-03679
Plan Check / Job No.
B23VN12311
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
17'-8" X 20'-2" ADDITION TO SFD FOR NEW BEDROOM AND BATHROOM
Permit Issued
Issued on 9/26/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/11/2023 APPLICANT
Assigned to Plan Check Engineer 9/15/2023 JEROME MAGAT PALMA
Corrections Issued 9/16/2023 JEROME MAGAT PALMA
Building Plans Picked Up 9/20/2023 APPLICANT
Plan Check Approved 9/26/2023 ALEC MOUSAKHANIAN
Issued 9/26/2023 APPLICANT
CofO in Progress 6/3/2024 RYAN SALAZAR
Permit Finaled 11/22/2024 RUBEN SALAS
CofO Issued 11/22/2024 RUBEN SALAS
Permit Finaled 11/22/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/22/2023 TAL SHEMEN
Roof/Waste drainage to street Cleared 9/22/2023 TAL SHEMEN
Sewer availability Cleared 9/22/2023 TAL SHEMEN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/12/2024 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 1/16/2024 Approved RYAN SALAZAR
Footing/Foundation/Slab 1/16/2024 Approved RYAN SALAZAR
Insulation 1/30/2024 Partial Approval RYAN SALAZAR
PLUMBING-Rough 1/30/2024 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 3/6/2024 Approved RYAN SALAZAR
ELECTRICAL-Rough 3/20/2024 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 3/20/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 3/20/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 3/27/2024 Approved RYAN SALAZAR
HVAC-Rough 3/27/2024 Approved RYAN SALAZAR
Insulation 3/27/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 3/27/2024 Partial Approval RYAN SALAZAR
Drywall Nailing 4/8/2024 Approved WILLIAM WREN
Interior/Exterior Lathing 4/8/2024 Partial Approval WILLIAM WREN
BUILDING-Rough-Frame 5/30/2024 Approved RYAN SALAZAR
ELECTRICAL-Final 5/30/2024 Approved RYAN SALAZAR
Final 5/30/2024 OK to Issue CofO RYAN SALAZAR
Green Building Final 5/30/2024 Approved RYAN SALAZAR
Green Building Rough 5/30/2024 Approved RYAN SALAZAR
HVAC-Final 5/30/2024 Approved RYAN SALAZAR
PLUMBING-Final 5/30/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/30/2024 SGSOV Approved RYAN SALAZAR
Smoke Detectors 5/30/2024 Approved RYAN SALAZAR