3947 N LAURELGROVE AVE 91604

Certificate Information: 3947 N LAURELGROVE AVE 91604

Application / Permit
23014-20000-03674
Plan Check / Job No.
B23VN12304
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMODEL (E) GARAGE AND ADD 21'-4" X 22'-4" 2ND FLOOR ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/14/2024
Issuing Office
Current Status
CofO Issued on 3/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/11/2023 APPLICANT
Assigned to Plan Check Engineer 9/14/2023 RAPHAEL ROSAS
Corrections Issued 9/21/2023 RAPHAEL ROSAS
Quality Review Completed 9/26/2023 STEVEN KIM
Building Plans Picked Up 9/29/2023 APPLICANT
Applicant returned to address corrections 12/21/2023 RAPHAEL ROSAS
Applicant returned to address corrections 2/20/2024 RAPHAEL ROSAS
Plan Check Approved 3/14/2024 RAPHAEL ROSAS
Issued 3/14/2024 APPLICANT
CofO in Progress 12/17/2024 CHRISTOPHE COCHRAN
Permit Finaled 3/6/2025 RUBEN SALAS
CofO Issued 3/6/2025 RUBEN SALAS
Permit Finaled 3/6/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/28/2023 NIKKI ZULUETA
Historic monument Cleared 9/28/2023 MELISSA JONES
Work Adjacent to Public Way Cleared 9/28/2023 NIKKI ZULUETA
ZI Cleared 9/28/2023 DAVID URITA
Eng Process Fee Ord 176,300 Cleared 10/2/2023 COLIN LOREDO
Sewer availability Cleared 10/2/2023 COLIN LOREDO
Hydrant and Access approval Cleared 10/7/2023 KURT CORRAL
Low Impact Development (LID) Cleared 1/9/2024 TRISH PARAS
Roof/Waste drainage to street Cleared 1/29/2024 COLIN LOREDO
Construction near power lines Cleared 1/31/2024 RIDWAN HARDY
GPI Written Notices Cleared 2/20/2024 RAPHAEL ROSAS
Grading Pre-Inspection Cleared 2/20/2024 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,
Engineer Khansa,, Eyass; Lic. No.: C91758 2252 JOSIE AVE      LONG BEACH, CA 90815

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/2/2024 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 5/3/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 5/3/2024 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 5/6/2024 Approved CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 5/7/2024 Conditional Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 5/10/2024 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 5/10/2024 Conditional Approval JUAN VALENZUELA
Special/Order Compliance 5/14/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 5/17/2024 Partial Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 5/21/2024 Conditional Approval CHRISTOPHE COCHRAN
Deputy Wood Construction 5/24/2024 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 7/3/2024 Approved CHRISTOPHE COCHRAN
Green Building Rough 7/3/2024 Approved CHRISTOPHE COCHRAN
Rough-Elec/Plmb/HVAC 7/3/2024 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 7/11/2024 Partial Approval CHRISTOPHE COCHRAN
Interior/Exterior Lathing 7/11/2024 Partial Approval CHRISTOPHE COCHRAN
Sewer 7/11/2024 Approved CHRISTOPHE COCHRAN
Insulation 7/22/2024 Approved CHRISTOPHE COCHRAN
Drywall Nailing 8/1/2024 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 9/4/2024 Approved CHRISTOPHE COCHRAN
Shower Pan 9/4/2024 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 11/14/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 12/4/2024 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 12/4/2024 Approved CHRISTOPHE COCHRAN
Green Building Final 12/4/2024 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 12/4/2024 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 12/4/2024 Approved CHRISTOPHE COCHRAN
Final 12/13/2024 OK to Issue CofO CHRISTOPHE COCHRAN
Service/Power Release 12/13/2024 Approved CHRISTOPHE COCHRAN