12303 W CANTURA ST 91604
Certificate Information: 12303 W CANTURA ST 91604
- Application / Permit
- 23014-20000-03673
- Plan Check / Job No.
- B23VN12304
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 270 SF ADDITIONS AND MAJOR REMODEL TO (E) SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 3/14/2024
- Issuing Office
- Current Status
- CofO Issued on 3/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2023 | RAPHAEL ROSAS |
| Corrections Issued | 9/21/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 9/26/2023 | STEVEN KIM |
| Building Plans Picked Up | 9/29/2023 | APPLICANT |
| Applicant returned to address corrections | 12/21/2023 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 2/20/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 3/14/2024 | RAPHAEL ROSAS |
| Issued | 3/14/2024 | APPLICANT |
| CofO in Progress | 12/17/2024 | CHRISTOPHE COCHRAN |
| Permit Finaled | 3/6/2025 | RUBEN SALAS |
| CofO Issued | 3/6/2025 | RUBEN SALAS |
| Permit Finaled | 3/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Historic monument | Cleared | 9/28/2023 | MELISSA JONES |
| ZI | Cleared | 9/28/2023 | DAVID URITA |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 9/30/2023 | NIKKI ZULUETA |
| Hydrant and Access approval | Cleared | 10/6/2023 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 1/9/2024 | TRISH PARAS |
| Roof/Waste drainage to street | Cleared | 1/26/2024 | JOHN LIN |
| GPI Written Notices | Cleared | 2/20/2024 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 2/20/2024 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khansa,, Eyass; Lic. No.: C91758 | 2252 JOSIE AVE LONG BEACH, CA 90815 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/2/2024 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 5/3/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 5/3/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 5/6/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 5/16/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Rough | 5/16/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 5/16/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 5/21/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Wood Frame | 5/21/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 5/24/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Insulation | 5/24/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 6/21/2024 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2024 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 6/21/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/21/2024 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 7/1/2024 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 7/1/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| HVAC-Rough | 7/2/2024 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 7/2/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Wood Frame | 7/2/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 7/3/2024 | Partial Inspection | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 7/3/2024 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 7/3/2024 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 7/3/2024 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 7/3/2024 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 7/11/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Sewer | 7/11/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 7/15/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 7/22/2024 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 8/1/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 9/3/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Shower Pan | 9/3/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 9/5/2024 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 11/14/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 12/4/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 12/4/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 12/4/2024 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 12/4/2024 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 12/4/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 12/13/2024 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Service/Power Release | 12/13/2024 | Approved | CHRISTOPHE COCHRAN |