11543 W ADDISON ST 91601

Certificate Information: 11543 W ADDISON ST 91601

Application / Permit
23014-20000-03660
Plan Check / Job No.
B23VN12270
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 14'6" x 40' irregular shape addition to the existing sfd, with interior remodel, also conversion part of the sfd and addition to it to make it a new attached garage to the sfd, total area of garage 361 sf. NFPA 13D sprinkler is required. All work done per engineer.
Permit Issued
Issued on 11/20/2023
Issuing Office
Current Status
CofO Issued on 4/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/11/2023 APPLICANT
Assigned to Plan Check Engineer 9/14/2023 NAREG ATARIAN
Corrections Issued 9/16/2023 NAREG ATARIAN
Quality Review Completed 9/20/2023 OMID HEDAYAT
Building Plans Picked Up 9/22/2023 APPLICANT
Applicant returned to address corrections 11/14/2023 NAREG ATARIAN
Plan Check Approved 11/20/2023 NAREG ATARIAN
Issued 11/20/2023 APPLICANT
CofO in Progress 3/18/2025 CHRISTOPHER ROJAS
Permit Finaled 4/10/2025 RUBEN SALAS
CofO Issued 4/10/2025 RUBEN SALAS
Permit Finaled 4/10/2025 RUBEN SALAS

Permit Application Clearance Information

Permit Cleared 9/23/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 9/25/2023 COLIN LOREDO
Sewer availability Cleared 9/25/2023 COLIN LOREDO
Specific Plan Cleared 9/26/2023 JOANNA MARROQUIN
Specific Plan Cleared 9/26/2023 JOANNA MARROQUIN
Hydrant and Access approval Cleared 10/8/2023 JOHN CONNEALLY
Low Impact Development (LID) Cleared 10/26/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 10/26/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/29/2024 Not Ready for Inspection KIRK SANDERS
Footing/Foundation/Slab 1/29/2024 Corrections Issued KIRK SANDERS
Special/Order Compliance 1/31/2024 Approved KIRK SANDERS
Excavation/Setback/Form/Re-Bar 2/2/2024 Partial Approval CRAIG DAVIS
Footing/Foundation/Slab 2/2/2024 Partial Approval CRAIG DAVIS
Deputy Drilled-In Anchors 2/15/2024 No Access for Inspection CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 2/15/2024 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 2/15/2024 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 3/6/2024 Approved KIRK SANDERS
Wood Frame 3/27/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Gas Test 4/5/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Underground Mechanical 4/5/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/9/2024 Corrections Issued KIRK SANDERS
Green Building Rough 4/9/2024 Not Ready for Inspection KIRK SANDERS
MERV13>=Rough 4/9/2024 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/15/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/20/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 6/20/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 6/20/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 6/20/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 6/20/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Deputy Wood Construction 6/24/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 6/28/2024 Partial Approval SALVADOR MARTINEZ
Rough-Elec/Plmb/HVAC 6/28/2024 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 7/2/2024 Approved CHRISTOPHER ROJAS
Wood Frame 7/2/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 8/1/2024 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/1/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 8/1/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 8/1/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 8/1/2024 Partial Approval CHRISTOPHER ROJAS
MERV13>=Rough 8/1/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 8/1/2024 Approved CHRISTOPHER ROJAS
Insulation 8/12/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 8/19/2024 Approved MICHAEL CORTEZ
Shower Pan 8/19/2024 Partial Approval MICHAEL CORTEZ
Interior/Exterior Lathing 9/12/2024 Approved CHRISTOPHER ROJAS
Shower Pan 9/12/2024 Approved CHRISTOPHER ROJAS
Sewer 11/26/2024 Approved CHRISTOPHER ROJAS
Underground Mechanical 11/26/2024 Approved CHRISTOPHER ROJAS
Final 1/6/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 1/6/2025 Partial Inspection CHRISTOPHER ROJAS
MERV13>=Final 1/6/2025 Approved CHRISTOPHER ROJAS
Reinforced Concrete Frame 1/6/2025 Partial Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 1/6/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 1/6/2025 Partial Inspection CHRISTOPHER ROJAS
Service/Power Release 1/13/2025 Approved CHRISTOPHER ROJAS
Final 3/12/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 3/12/2025 Approved CHRISTOPHER ROJAS
Reinforced Concrete Frame 3/12/2025 Partial Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 3/12/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 3/12/2025 Approved CHRISTOPHER ROJAS
Final 3/17/2025 OK to Issue CofO CHRISTOPHER ROJAS
Reinforced Concrete Frame 3/17/2025 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 3/17/2025 SGSOV Approved CHRISTOPHER ROJAS