13311 W HERRON ST 91342

Certificate Information: 13311 W HERRON ST 91342

Application / Permit
23014-20000-03651
Plan Check / Job No.
B23VN12243
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 5'-6" x 9'-10" BATHROOM ADDITION TO (E) SFD. WORK DONE PER ENGINEERING.
Permit Issued
Issued on 9/28/2023
Issuing Office
Current Status
CofO Issued on 4/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2023 APPLICANT
Assigned to Plan Check Engineer 9/13/2023 MIROOSH KHACHATOORIAN
Corrections Issued 9/14/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 9/26/2023 MOHAMMAD ESMAILI
Issued 9/28/2023 APPLICANT
CofO in Progress 4/10/2024 ROBERT GOLD
CofO Issued 4/11/2024 RUBEN SALAS
Permit Finaled 4/11/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/18/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/22/2023 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Yu,, Jennifer Arianna; Lic. No.: C79156 3828 EARLE AVE      ROSEMEAD, CA 91770

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/2/2024 Approved KEVIN BERBERYAN
PLUMBING-Rough 1/2/2024 Approved KEVIN BERBERYAN
Reinforced Concrete Frame 1/2/2024 Partial Inspection KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 1/12/2024 Partial Approval KEVIN BERBERYAN
Wood Frame 1/12/2024 Partial Inspection KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 1/17/2024 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 1/30/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 1/30/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 1/30/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 1/30/2024 Approved CHRISTOPHER ROJAS
Insulation 1/30/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 1/30/2024 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 2/2/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 2/2/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 2/2/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 2/2/2024 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 2/2/2024 Approved CHRISTOPHER ROJAS
Wood Frame 2/2/2024 Approved CHRISTOPHER ROJAS
Insulation 2/8/2024 Approved JOHN COLEMAN
Drywall Nailing 2/14/2024 Approved JOHN COLEMAN
Shower Pan 2/14/2024 Approved JOHN COLEMAN
Final 2/27/2024 Corrections Issued KEVIN BERBERYAN
Green Building Final 2/27/2024 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 2/27/2024 SGSOV Not Ready KEVIN BERBERYAN
Smoke Detectors 2/27/2024 Approved KEVIN BERBERYAN
Final 3/5/2024 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 3/5/2024 SGSOV Not Ready KEVIN BERBERYAN
Final 3/7/2024 OK to Issue CofO KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 3/7/2024 SGSOV Approved KEVIN BERBERYAN