4380-4382 S MCCONNELL AVE 90066

Certificate Information: 4380-4382 S MCCONNELL AVE 90066

Application / Permit
23014-20000-03622
Plan Check / Job No.
B23VN12183
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO JUNIOR ACCCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22. ADDITIONS TO EX. SFD FOR NEW ENTRY PORCH, NEW BATHROOM, AND LAUNDRY ROOM. REMODEL EX. SFD, REMOVE WALLS PER PLANS. WORK PER ENGINEER.
Permit Issued
Issued on 10/18/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/8/2023 APPLICANT
Assigned to Plan Check Engineer 9/13/2023 ARTIN ZARUKIAN
Corrections Issued 9/16/2023 ARTIN ZARUKIAN
Building Plans Picked Up 9/18/2023 APPLICANT
Plan Check Approved 10/4/2023 ROSENDO MEDINA
Issued 10/18/2023 APPLICANT
CofO in Progress 4/11/2024 TEMISTOCLES CAAL
Permit Finaled 4/12/2024 DANIEL ORRANTE
CofO Issued 4/12/2024 DANIEL ORRANTE
Permit Finaled 4/12/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/18/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 9/18/2023 DARIN LAM
Roof/Waste drainage to street Cleared 9/18/2023 DARIN LAM
Sewer availability Cleared 9/18/2023 DARIN LAM
Specific Plan Cleared 9/18/2023 WESTON PRINGLE

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/28/2023 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 12/4/2023 Corrections Issued HERBERT GIRON
Deputy Drilled-In Anchors 12/6/2023 Conditional Approval RICHARD STEINBACH
Deputy Drilled-In Anchors 12/13/2023 Conditional Approval MICHAEL PELHAM
Deputy Wood Construction 12/13/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 12/14/2023 Approved TEMISTOCLES CAAL
PLUMBING-Rough 12/14/2023 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 12/15/2023 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 1/16/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 1/18/2024 Approved TEMISTOCLES CAAL
HVAC-Rough 1/18/2024 Approved TEMISTOCLES CAAL
PLUMBING-Rough 1/18/2024 Approved TEMISTOCLES CAAL
Shower Pan 1/24/2024 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 2/1/2024 Approved TEMISTOCLES CAAL
Green Building Rough 2/1/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 2/1/2024 Approved TEMISTOCLES CAAL
Insulation 2/7/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 2/9/2024 Approved TEMISTOCLES CAAL
Sewer 2/13/2024 Approved JESUS RODRIGUEZ
Underground Mechanical 2/13/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 4/9/2024 Corrections Issued TEMISTOCLES CAAL
Final 4/9/2024 Corrections Issued TEMISTOCLES CAAL
Gas Test 4/9/2024 Approved TEMISTOCLES CAAL
Green Building Final 4/9/2024 Approved TEMISTOCLES CAAL
HVAC-Final 4/9/2024 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Final 4/9/2024 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 4/9/2024 SGSOV Approved TEMISTOCLES CAAL
Smoke Detectors 4/9/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 4/10/2024 Approved TEMISTOCLES CAAL
Final 4/10/2024 OK to Issue CofO TEMISTOCLES CAAL
HVAC-Final 4/10/2024 Approved TEMISTOCLES CAAL
Service/Power Release 4/10/2024 Approved TEMISTOCLES CAAL