4380-4382 S MCCONNELL AVE 90066
Certificate Information: 4380-4382 S MCCONNELL AVE 90066
- Application / Permit
- 23014-20000-03622
- Plan Check / Job No.
- B23VN12183
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE TO JUNIOR ACCCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22. ADDITIONS TO EX. SFD FOR NEW ENTRY PORCH, NEW BATHROOM, AND LAUNDRY ROOM. REMODEL EX. SFD, REMOVE WALLS PER PLANS. WORK PER ENGINEER.
- Permit Issued
- Issued on 10/18/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 9/16/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 9/18/2023 | APPLICANT |
| Plan Check Approved | 10/4/2023 | ROSENDO MEDINA |
| Issued | 10/18/2023 | APPLICANT |
| CofO in Progress | 4/11/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 4/12/2024 | DANIEL ORRANTE |
| CofO Issued | 4/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/18/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2023 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 9/18/2023 | DARIN LAM |
| Sewer availability | Cleared | 9/18/2023 | DARIN LAM |
| Specific Plan | Cleared | 9/18/2023 | WESTON PRINGLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/28/2023 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 12/4/2023 | Corrections Issued | HERBERT GIRON |
| Deputy Drilled-In Anchors | 12/6/2023 | Conditional Approval | RICHARD STEINBACH |
| Deputy Drilled-In Anchors | 12/13/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 12/13/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 12/14/2023 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 12/14/2023 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2023 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 1/18/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 1/18/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 1/18/2024 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 1/24/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 2/1/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 2/1/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 2/1/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 2/7/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 2/9/2024 | Approved | TEMISTOCLES CAAL |
| Sewer | 2/13/2024 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 2/13/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 4/9/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Final | 4/9/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Gas Test | 4/9/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Final | 4/9/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 4/9/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 4/9/2024 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 4/9/2024 | SGSOV Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 4/9/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 4/10/2024 | Approved | TEMISTOCLES CAAL |
| Final | 4/10/2024 | OK to Issue CofO | TEMISTOCLES CAAL |
| HVAC-Final | 4/10/2024 | Approved | TEMISTOCLES CAAL |
| Service/Power Release | 4/10/2024 | Approved | TEMISTOCLES CAAL |