5761 N LEMP AVE 91601
Certificate Information: 5761 N LEMP AVE 91601
- Application / Permit
- 23014-20000-03616
- Plan Check / Job No.
- B23VN12159
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD TO & CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 7/12/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2023 | JESSE ARELLANO |
| Corrections Issued | 9/16/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 9/19/2023 | APPLICANT |
| Plan Check Approved | 10/17/2023 | PINANK PATEL |
| Issued | 7/12/2024 | APPLICANT |
| CofO in Progress | 2/4/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 2/27/2025 | RUBEN SALAS |
| CofO Issued | 2/27/2025 | RUBEN SALAS |
| Permit Finaled | 2/27/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/4/2023 | NIKKI ZULUETA |
| Roof/Waste drainage to street | Cleared | 10/4/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 10/10/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/18/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 8/27/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Underground Mechanical | 8/27/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Deputy Drilled-In Anchors | 9/4/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 9/4/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Sewer | 9/4/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 10/2/2024 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 10/2/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/16/2024 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 10/16/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 10/16/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 10/16/2024 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/16/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/21/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 10/21/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/21/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 10/25/2024 | Approved | LOUIS ESCOTO |
| Shower Pan | 10/25/2024 | Not Ready for Inspection | LOUIS ESCOTO |
| Drywall Nailing | 10/31/2024 | Corrections Issued | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 10/31/2024 | Not Ready for Inspection | MICHAEL CORTEZ |
| Shower Pan | 10/31/2024 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 11/4/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Final | 12/30/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 12/30/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Final | 12/30/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 12/30/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 12/30/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 1/13/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 1/13/2025 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 1/13/2025 | SGSOV Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 1/16/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 1/23/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 1/23/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |