8055 N MATILIJA AVE 91402

Certificate Information: 8055 N MATILIJA AVE 91402

Application / Permit
23014-20000-03608
Plan Check / Job No.
B23VN12133
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE ONE STORY ADDITION AND MAJOR REMODE TO (E) SFD [LEAVING ONE WALL/FOOTING AT 19' IN LENGTH] _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 11/8/2023
Issuing Office
Current Status
Issued on 11/8/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/7/2023 APPLICANT
Assigned to Plan Check Engineer 9/14/2023 DAWN MC NULTY
Corrections Issued 9/22/2023 DAWN MC NULTY
Quality Review Completed 9/22/2023 STEVEN KIM
Building Plans Picked Up 9/27/2023 APPLICANT
Plan Check Approved 11/8/2023 DAWN MC NULTY
Issued 11/8/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/23/2023 COLIN LOREDO
Sewer availability Cleared 10/23/2023 COLIN LOREDO
Low Impact Development (LID) Cleared 10/24/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 10/27/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/8/2023 Approved GREGG CUMMINGS
Special/Order Compliance 12/8/2023 Approved GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 1/26/2024 Approved GREGG CUMMINGS
Footing/Foundation/Slab 1/26/2024 Approved GREGG CUMMINGS
PLUMBING-Rough 2/23/2024 Partial Approval GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 2/28/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 3/14/2024 Approved CHRISTOPHER ROJAS
Special/Order Compliance 3/14/2024 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 4/2/2024 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 4/2/2024 Approved CHRISTOPHER ROJAS
Wood Frame 4/2/2024 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/14/2024 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/14/2024 Approved VINCENT HANLEY
HVAC-Rough 5/14/2024 Approved VINCENT HANLEY
PLUMBING-Rough 5/14/2024 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/21/2024 Approved VINCENT HANLEY
PLUMBING-Rough 5/21/2024 Approved VINCENT HANLEY
Special/Order Compliance 5/21/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 6/7/2024 Corrections Issued GREGG CUMMINGS
Insulation 6/7/2024 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 6/12/2024 Approved VINCENT HANLEY
Green Building Rough 6/12/2024 Approved VINCENT HANLEY
Insulation 6/12/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 6/12/2024 Partial Approval VINCENT HANLEY
Verify Sprinkler Sign Off 6/12/2024 Approved VINCENT HANLEY
Drywall Nailing 8/5/2024 Approved GREGG CUMMINGS
Shower Pan 9/9/2024 Approved GREGG CUMMINGS
Special/Order Compliance 9/9/2024 Corrections Issued GREGG CUMMINGS
Smoke Detectors 10/24/2024 Not Ready for Inspection GREGG CUMMINGS
Special/Order Compliance 10/24/2024 Not Ready for Inspection GREGG CUMMINGS
Final 12/2/2024 Corrections Issued GREGG CUMMINGS
Green Building Final 12/2/2024 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 12/2/2024 SGSOV Not Ready GREGG CUMMINGS
Smoke Detectors 12/2/2024 Not Ready for Inspection GREGG CUMMINGS
Final 5/7/2026 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 5/7/2026 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 5/7/2026 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 5/7/2026 Approved OGANES TARAKHCHYAN
Smoke Detectors 5/7/2026 Approved OGANES TARAKHCHYAN