1418 W CRUCES ST 90744
Certificate Information: 1418 W CRUCES ST 90744
- Application / Permit
- 23014-20000-03598
- Plan Check / Job No.
- B23VN12103
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 13'-0" X 30'-0" PATIO COVER ADDITION TO (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 10/20/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/7/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 9/7/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 10/18/2023 | JEROME MAGAT PALMA |
| Issued | 10/20/2023 | APPLICANT |
| CofO in Progress | 11/13/2023 | EUGENE CASSIDY |
| CofO Issued | 11/13/2023 | ANSON MAGLASANG |
| Permit Finaled | 11/13/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/12/2023 | KHAING AYE |
| Drainage to Storm Drain | Cleared | 10/18/2023 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2023 | KHAING AYE |
Contact Information
| Contractor | G & S Developers Inc; Lic. No.: 1060472-B | 12815 MORRISON ST VALLEY VILLAGE, CA 91607 |
| Engineer | Putnam,, Carl Matthew; Lic. No.: C68139 | 3441 IVYLINK PL LYNCHBURG, VA 24503 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/30/2023 | Corrections Issued | EUGENE CASSIDY |
| METHANE-Rough | 10/30/2023 | No Access for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/2/2023 | Partial Approval | EUGENE CASSIDY |
| METHANE-Rough | 11/2/2023 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/7/2023 | Approved | EUGENE CASSIDY |
| Final | 11/7/2023 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 11/7/2023 | Approved | EUGENE CASSIDY |
| METHANE-Barrier | 11/7/2023 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 11/7/2023 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 11/7/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 11/9/2023 | Approved | EUGENE CASSIDY |
| Final | 11/9/2023 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 11/9/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 11/9/2023 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 11/9/2023 | Approved | EUGENE CASSIDY |