4114-4116 S ALLA ROAD 90066
Certificate Information: 4114-4116 S ALLA ROAD 90066
- Application / Permit
- 23014-20000-03587
- Plan Check / Job No.
- B23VN12068
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story Addition to create an attached Accessory Dwelling Unit (21' x 17'-10") per LAMC 12.22 A.33 (c) and (e).
- Permit Issued
- Issued on 10/26/2023
- Issuing Office
- Current Status
- CofO Issued on 10/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2023 | VAHAN JIVALAGIAN |
| Corrections Issued | 9/15/2023 | VAHAN JIVALAGIAN |
| Quality Review Completed | 9/15/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 9/19/2023 | APPLICANT |
| Plan Check Approved | 10/25/2023 | VAHAN JIVALAGIAN |
| Issued | 10/26/2023 | APPLICANT |
| CofO in Progress | 10/3/2024 | TEMISTOCLES CAAL |
| CofO Issued | 10/9/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/9/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 9/25/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/26/2023 | DARIN LAM |
| Sewer availability | Cleared | 9/26/2023 | DARIN LAM |
| Specific Plan | Cleared | 10/4/2023 | ALESSANDRO MERCURI |
| Roof/Waste drainage to street | Cleared | 10/13/2023 | DARIN LAM |
Contact Information
| Contractor | Built To Perfection Inc; Lic. No.: 837987-B | 22222 SHERMAN WAY #202 CANOGA PARK, CA 91303 |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 12/11/2023 | No Access for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 12/12/2023 | Partial Approval | JESUS RODRIGUEZ |
| Deputy Drilled-In Anchors | 12/18/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 12/19/2023 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 12/19/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Wood Frame | 1/26/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2024 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 3/22/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 3/22/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/22/2024 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 3/22/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 4/3/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 4/3/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 4/10/2024 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 4/10/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 4/10/2024 | Approved | JESUS RODRIGUEZ |
| Sewer | 8/8/2024 | Approved | HERBERT GIRON |
| Underground Mechanical | 8/8/2024 | Partial Approval | HERBERT GIRON |
| Final | 9/20/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 9/20/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 9/20/2024 | SGSOV Not Required | JESUS PINEDA |
| Smoke Detectors | 9/20/2024 | Approved | JESUS PINEDA |
| Final | 10/2/2024 | OK to Issue CofO | TEMISTOCLES CAAL |
| Service/Power Release | 10/8/2024 | Approved | TEMISTOCLES CAAL |