5102 N ESCOBEDO DR 91364

Certificate Information: 5102 N ESCOBEDO DR 91364

Application / Permit
23014-20000-03586
Plan Check / Job No.
B23VN12066
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) LAUNDRY AND PORTION OF KITCHEN TO NEW BEDROOM AND ENCLOSE 5' X 1'-5" PORTION OF (E) CARPORT TO CLOSET. CONVERT PORTION OF (E) BEDROOM TO NEW BATHROOM.
Permit Issued
Issued on 9/27/2023
Issuing Office
Valley
Current Status
CofO Issued on 7/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2023 APPLICANT
Assigned to Plan Check Engineer 9/6/2023 GIOVANNY CHAVEZ
Corrections Issued 9/6/2023 GIOVANNY CHAVEZ
Applicant returned to address corrections 9/22/2023 ANGELICA DAVE
Plan Check Approved 9/27/2023 ALEC MOUSAKHANIAN
Issued 9/27/2023 APPLICANT
CofO in Progress 6/14/2024 JOHN HAYES
Permit Finaled 7/10/2024 JOHN JANSON
CofO Issued 7/10/2024 JOHN JANSON
Permit Finaled 7/10/2024 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/8/2023 ROMAN GUTIERREZ
Sewer availability Cleared 9/8/2023 ROMAN GUTIERREZ
Grading Pre-Inspection Cleared 9/19/2023 CHARLES POWELL

Contact Information

Contractor Highlight Remodeling Inc; Lic. No.: 1064710-B 20929 VENTURA BLVD STE 47      WOODLAND HILLS, CA 91364
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 10/12/2023 Not Ready for Inspection PETER FOLLING
Footing/Foundation/Slab 10/12/2023 Approved PETER FOLLING
Green Building Rough 10/12/2023 Not Ready for Inspection PETER FOLLING
HVAC-Rough 10/12/2023 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 10/12/2023 Partial Approval PETER FOLLING
ELECTRICAL-Rough 10/16/2023 No Access for Inspection PETER FOLLING
HVAC-Rough 10/16/2023 No Access for Inspection PETER FOLLING
Shower Pan 10/18/2023 Approved PETER FOLLING
ELECTRICAL-Rough 10/20/2023 Corrections Issued PETER FOLLING
ELECTRICAL-Rough 12/11/2023 Approved JOHN KIDWELL
HVAC-Rough 12/11/2023 Approved JOHN KIDWELL
PLUMBING-Rough 12/11/2023 Approved JOHN KIDWELL
BUILDING-Rough-Frame 12/29/2023 Approved VINCENT HANLEY
Drywall Nailing 12/29/2023 Approved VINCENT HANLEY
Green Building Rough 12/29/2023 Approved VINCENT HANLEY
Final 6/1/2024 Corrections Issued RYAN SALAZAR
Green Building Final 6/1/2024 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 6/1/2024 SGSOV Not Ready RYAN SALAZAR
Smoke Detectors 6/1/2024 Approved RYAN SALAZAR
Final 6/6/2024 Corrections Issued JOHN HAYES
Green Building Final 6/6/2024 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 6/6/2024 SGSOV Approved JOHN HAYES
Final 6/8/2024 OK to Issue CofO MISAEL ESPARZA