7331-7331 1/2 N KRAFT AVE 91605

Certificate Information: 7331-7331 1/2 N KRAFT AVE 91605

Application / Permit
23014-20000-03532
Plan Check / Job No.
B23VN11919
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d); ADD 19' X 23' NEW DWELLING PER SB9; EQUIPPED WITH NFPA -13D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/9/2024
Issuing Office
Valley
Current Status
CofO Issued on 8/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/1/2023 APPLICANT
Assigned to Plan Check Engineer 9/7/2023 SELLA BENYAMIN
Corrections Issued 9/14/2023 SELLA BENYAMIN
Quality Review Completed 9/14/2023 STEVEN KIM
Building Plans Picked Up 9/21/2023 APPLICANT
Plan Check Approved 5/9/2024 SELLA BENYAMIN
Issued 5/9/2024 APPLICANT
CofO in Progress 8/5/2025 ROBERTO PALACIOS-LOPEZ
Permit Finaled 8/28/2025 RUBEN SALAS
CofO Issued 8/28/2025 RUBEN SALAS
Permit Finaled 8/28/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/16/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/16/2023 COLIN LOREDO
Roof/Waste drainage to street Cleared 10/16/2023 COLIN LOREDO
Sewer availability Cleared 10/16/2023 COLIN LOREDO
Senate Bill 9 Cleared 1/10/2024 ALEX VELA
Construction near power lines Cleared 4/26/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/11/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Pre-Inspection 6/11/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 6/14/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Gas Test 6/14/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 6/14/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Pre-Inspection 6/14/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Sewer 6/14/2024 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 6/14/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 6/25/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 7/5/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 8/15/2024 Approved JOSE AVILA
PLUMBING-Rough 8/15/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 8/23/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 8/23/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 8/28/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 8/28/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 8/30/2024 No Access for Inspection JOSE AVILA
ELECTRICAL-Rough 9/3/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 9/3/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 9/3/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 9/3/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Underground Mechanical 9/3/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 10/25/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 10/25/2024 Approved ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 10/25/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 10/25/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 10/25/2024 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 10/25/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 11/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 12/27/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 1/13/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 1/13/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 1/13/2025 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 1/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Drywall Nailing 1/24/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Shower Pan 1/31/2025 Approved MICHAEL CORTEZ
ELECTRICAL-Final 4/23/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 4/23/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 4/23/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 6/4/2025 Approved MISAEL ESPARZA
ELECTRICAL-Final 6/20/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 6/20/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 6/20/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 6/20/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 6/20/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 6/20/2025 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 6/20/2025 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 7/11/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 7/11/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 7/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 7/11/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 8/5/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ