6558 N BUFFALO AVE 91401
Certificate Information: 6558 N BUFFALO AVE 91401
- Application / Permit
- 23014-20000-03497
- Plan Check / Job No.
- B23VN11743
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 19'3" x 18' DETACHED GARAGE WITH 15' x 16'-0" ADDITION INTO A (N) ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c) AND (d) PER WFPP AND ENGINEER DETAIL.
- Permit Issued
- Issued on 11/27/2023
- Issuing Office
- Current Status
- CofO Issued on 5/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2023 | ALFRED RAMIREZ |
| Corrections Issued | 9/6/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 11/8/2023 | MADISON ODELL |
| Applicant returned to address corrections | 11/11/2023 | MADISON ODELL |
| Plan Check Approved | 11/25/2023 | MADISON O'DELL |
| Issued | 11/27/2023 | APPLICANT |
| CofO in Progress | 5/23/2024 | JOSE AVILA |
| Permit Finaled | 5/29/2024 | RUBEN SALAS |
| CofO Issued | 5/29/2024 | RUBEN SALAS |
| Permit Finaled | 5/29/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/11/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2023 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 10/31/2023 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 11/8/2023 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/18/2023 | Partial Approval | JOSE AVILA |
| Deputy Drilled-In Anchors | 12/27/2023 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 12/28/2023 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 1/9/2024 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2024 | Corrections Issued | JOSE AVILA |
| Gas Test | 2/13/2024 | Partial Approval | MISAEL ESPARZA |
| Underground Mechanical | 2/13/2024 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 2/15/2024 | Approved | JOSE AVILA |
| Underground Mechanical | 2/15/2024 | Partial Inspection | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2024 | Approved | JOSE AVILA |
| HVAC-Rough | 2/21/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 2/21/2024 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 2/26/2024 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 2/28/2024 | Approved | JOSE AVILA |
| Insulation | 2/28/2024 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 2/28/2024 | Approved | JOSE AVILA |
| Drywall Nailing | 3/1/2024 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 4/22/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 4/22/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 4/22/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 4/22/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 4/22/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/22/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 4/22/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 4/24/2024 | Approved | JOSE AVILA |
| Final | 4/24/2024 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 4/24/2024 | Conditional Approval | JOSE AVILA |
| PLUMBING-Final | 4/24/2024 | Approved | JOSE AVILA |
| Final | 4/26/2024 | Partial Approval | JOSE AVILA |
| Deputy Reinf. Concrete | 5/23/2024 | Approved | JOSE AVILA |
| Final | 5/23/2024 | OK to Issue CofO | JOSE AVILA |
| Service/Power Release | 5/23/2024 | Approved | JOSE AVILA |