12053 N ADELPHIA AVE 91340
Certificate Information: 12053 N ADELPHIA AVE 91340
- Application / Permit
- 23014-20000-03489
- Plan Check / Job No.
- B23VN11691
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: 6'6" X 18' ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ATTACHED LAUNDRY ROOM. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 10/26/2023
- Issuing Office
- Current Status
- Issued on 10/26/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2023 | OMAR GARNICA |
| Corrections Issued | 9/9/2023 | OMAR GARNICA |
| Plan Check Approved | 10/17/2023 | OMAR GARNICA |
| Issued | 10/26/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/7/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 10/7/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/12/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Warren Development Llc; Lic. No.: 1098736-B | , |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/30/2023 | Approved | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 2/2/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 2/2/2024 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 2/7/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/12/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/12/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/13/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 2/13/2024 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 2/13/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/13/2024 | Approved | MICHEL ABAJAN |
| Deputy Wood Construction | 2/15/2024 | Conditional Approval | ROBERT GOLD |
| Insulation | 2/15/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 2/20/2024 | Approved | MICHEL ABAJAN |
| Shower Pan | 2/20/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/22/2024 | Approved | MICHEL ABAJAN |
| Final | 3/15/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Final | 3/15/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Final | 3/15/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 3/15/2024 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 3/15/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 3/19/2024 | Approved | MICHEL ABAJAN |
| Final | 3/19/2024 | Partial Inspection | MICHEL ABAJAN |
| Green Building Final | 3/19/2024 | Approved | MICHEL ABAJAN |
| HVAC-Final | 3/19/2024 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 3/19/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 3/19/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 3/19/2024 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 3/19/2024 | Approved | MICHEL ABAJAN |