15116 W POLK ST 91342

Certificate Information: 15116 W POLK ST 91342

Application / Permit
23014-20000-03488
Plan Check / Job No.
B23VN11674
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
9'-0" X 17'-8" ADDITION AND CONVERT EXISTING 23'-0" X 21'-0" DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) - PER WFPP ***SEE COMMENTS
Permit Issued
Issued on 10/13/2023
Issuing Office
Current Status
CofO Issued on 8/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/29/2023 APPLICANT
Assigned to Plan Check Engineer 9/1/2023 DANIEL ABRAMYAN
Corrections Issued 9/3/2023 DANIEL ABRAMYAN
Applicant returned to address corrections 10/12/2023 DANIEL ABRAMYAN
Plan Check Approved 10/13/2023 OMAR GARNICA
Issued 10/13/2023 APPLICANT
CofO in Progress 8/11/2025 JENNIFER RABUCHIN
Permit Finaled 8/20/2025 RUBEN SALAS
CofO Issued 8/20/2025 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/19/2023 MICHAEL TEMPLE
Address approval Cleared 9/20/2023 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 9/20/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 9/30/2023 NIKKI ZULUETA
Sewer availability Cleared 9/30/2023 NIKKI ZULUETA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/7/2024 Corrections Issued WILLIAM WREN
Pre-Inspection 6/7/2024 Not Ready for Inspection WILLIAM WREN
Pre-Inspection 6/11/2024 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 10/2/2024 Approved JENNIFER RABUCHIN
PLUMBING-Rough 11/8/2024 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/26/2024 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 11/26/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 11/26/2024 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 11/26/2024 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/2/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 12/2/2024 Approved JENNIFER RABUCHIN
Green Building Rough 12/2/2024 Approved JENNIFER RABUCHIN
HVAC-Rough 12/2/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 12/2/2024 Partial Approval JENNIFER RABUCHIN
Insulation 12/6/2024 Corrections Issued MICHAEL CORTEZ
Drywall Nailing 12/10/2024 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/13/2024 Approved JENNIFER RABUCHIN
Drywall Nailing 12/16/2024 Approved JENNIFER RABUCHIN
HVAC-Final 7/3/2025 Not Ready for Inspection JENNIFER RABUCHIN
Service/Power Release 7/3/2025 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 7/10/2025 Corrections Issued JENNIFER RABUCHIN
Final 7/10/2025 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 7/10/2025 Approved JENNIFER RABUCHIN
HVAC-Final 7/10/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 7/10/2025 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/10/2025 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 7/10/2025 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 7/10/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 7/25/2025 Corrections Issued JENNIFER RABUCHIN
Final 7/25/2025 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Final 7/25/2025 Approved JENNIFER RABUCHIN
Service/Power Release 7/25/2025 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 8/5/2025 Approved JENNIFER RABUCHIN
Final 8/5/2025 OK to Issue CofO JENNIFER RABUCHIN
Service/Power Release 8/5/2025 Approved JENNIFER RABUCHIN