17179 W MCKEEVER ST 91344

Certificate Information: 17179 W MCKEEVER ST 91344

Application / Permit
23014-20000-03467
Plan Check / Job No.
B23VN10676
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ATTACHED 18' X 18' CARPORT TO (E) SINGLE FAMILY DWELLING PER LADBS IB REQUIRED PARKING FOR SB-9 UNIT UNDER 23010-20000-03222
Permit Issued
Issued on 8/6/2024
Issuing Office
Current Status
CofO Issued on 6/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2023 APPLICANT
Assigned to Plan Check Engineer 8/24/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 8/29/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 9/1/2023 OMID HEDAYAT
Applicant returned to address corrections 6/27/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 7/30/2024 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 8/1/2024 SEWADA ZADOORAN MILAGARDI
Issued 8/6/2024 APPLICANT
CofO in Progress 4/15/2025 DAVID SCANTLIN
CofO in Progress 5/16/2025 STEVEN BACK
CofO in Progress 5/16/2025 STEVEN BACK
CofO in Progress 5/20/2025 STEVEN BACK
CofO in Progress 6/25/2025 STEVEN BACK
Permit Finaled 6/27/2025 JOHN JANSON
CofO Issued 6/27/2025 JOHN JANSON
Permit Finaled 6/27/2025 JOHN JANSON

Permit Application Clearance Information

Low Impact Development (LID) Cleared 5/31/2024 ANDRES COVARRUBIAS
Eng Process Fee Ord 176,300 Cleared 6/3/2024 KENIA CASTILLO
Roof/Waste drainage to street Cleared 6/7/2024 KENIA CASTILLO
GPI Written Notices Cleared 7/30/2024 SEWADA ZADOORAN MILAGARDI
Grading Pre-Inspection Cleared 7/30/2024 SEWADA ZADOORAN MILAGARDI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/22/2024 Not Ready for Inspection STEVEN BACK
Footing/Foundation/Slab 9/5/2024 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/30/2024 Approved STEVEN BACK
BUILDING-Rough-Frame 10/11/2024 Approved STEVEN BACK
Final 10/11/2024 Corrections Issued STEVEN BACK
Green Building Final 10/11/2024 Approved STEVEN BACK
Green Building Rough 10/11/2024 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 10/11/2024 SGSOV Not Ready STEVEN BACK
Smoke Detectors 10/11/2024 Approved STEVEN BACK
Final 3/19/2025 Corrections Issued STEVEN BACK
SGSOV-Seismic Gas S/O Valve 3/19/2025 SGSOV Not Ready STEVEN BACK
Final 4/14/2025 Corrections Issued DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 4/14/2025 SGSOV Approved DAVID SCANTLIN
Final 5/20/2025 Corrections Issued STEVEN BACK
Final 6/25/2025 OK to Issue CofO STEVEN BACK