11325-11327 N MONOGRAM AVE 91344

Certificate Information: 11325-11327 N MONOGRAM AVE 91344

Application / Permit
23014-20000-03434
Plan Check / Job No.
B23VN11501
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN. PROPOSED ADU 500 S.F BEING ADDED TO (E) SFD AND ATTACHED GARAGE PER STATE LAW
Permit Issued
Issued on 12/4/2023
Issuing Office
Current Status
CofO Issued on 5/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2023 APPLICANT
Assigned to Plan Check Engineer 8/29/2023 JOSEPH RAFOLS
Corrections Issued 8/30/2023 JOSEPH RAFOLS
Applicant returned to address corrections 11/1/2023 DANIEL SANJUAN
Applicant returned to address corrections 11/22/2023 NEHEMIAS RAMOS
Plan Check Approved 12/3/2023 KHUONG TRUONG
Issued 12/4/2023 APPLICANT
CofO in Progress 5/20/2024 JAVIER RAMOS JR
Permit Finaled 5/31/2024 RUBEN SALAS
CofO Issued 5/31/2024 RUBEN SALAS
Permit Finaled 5/31/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/31/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 9/8/2023 TAL SHEMEN
Sewer availability Cleared 9/8/2023 TAL SHEMEN
Low Impact Development (LID) Cleared 10/20/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 10/23/2023 COLIN LOREDO
GPI Written Notices Cleared 12/3/2023 JOSEPH RAFOLS
Grading Pre-Inspection Cleared 12/3/2023 JOSEPH RAFOLS

Contact Information

Architect Hamlet, Sadekyan; Lic. No.: C39815       ,
Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/9/2024 Partial Approval MICHEL ABAJAN
Deputy Drilled-In Anchors 1/10/2024 Conditional Approval JAVIER RAMOS JR
Footing/Foundation/Slab 1/11/2024 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 2/16/2024 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 2/16/2024 Approved JAVIER RAMOS JR
HVAC-Rough 2/16/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 2/16/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 2/23/2024 Not Ready for Inspection JAVIER RAMOS JR
Green Building Rough 2/23/2024 Approved JAVIER RAMOS JR
Insulation 2/23/2024 Partial Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 2/23/2024 Partial Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 2/26/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 3/4/2024 Partial Approval JAVIER RAMOS JR
Drywall Nailing 3/4/2024 Approved JAVIER RAMOS JR
Insulation 3/4/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 3/4/2024 Approved JAVIER RAMOS JR
Sewer 4/9/2024 Approved JAVIER RAMOS JR
Underground Mechanical 4/9/2024 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Final 5/6/2024 Corrections Issued JOHN COLEMAN
Final 5/6/2024 Corrections Issued JOHN COLEMAN
Green Building Final 5/6/2024 Approved JOHN COLEMAN
HVAC-Final 5/6/2024 Approved JOHN COLEMAN
PLUMBING-Final 5/6/2024 Approved JOHN COLEMAN
BUILDING-Rough-Frame 5/20/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 5/20/2024 Approved JAVIER RAMOS JR
Final 5/20/2024 OK to Issue CofO JAVIER RAMOS JR
MERV13>=Final 5/20/2024 Approved JAVIER RAMOS JR
MERV13>=Rough 5/20/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/20/2024 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 5/20/2024 Approved JAVIER RAMOS JR