7513 N YARMOUTH AVE 91335

Certificate Information: 7513 N YARMOUTH AVE 91335

Application / Permit
23014-20000-03430
Plan Check / Job No.
B23VN11492
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 19'-3" X 50' DET. ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK PER ENGINEER.
Permit Issued
Issued on 2/22/2024
Issuing Office
Valley
Current Status
CofO Issued on 4/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2023 APPLICANT
Assigned to Plan Check Engineer 8/31/2023 JESSE ARELLANO
Corrections Issued 9/2/2023 JESSE ARELLANO
Building Plans Picked Up 9/19/2023 APPLICANT
Applicant returned to address corrections 10/5/2023 KAMYAR EMAMI
Applicant returned to address corrections 11/28/2023 SERGIO MUNIZ
Applicant returned to address corrections 12/1/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 12/7/2023 MADISON ODELL
Applicant returned to address corrections 2/15/2024 ANGELICA DAVE
Plan Check Approved 2/20/2024 JESSE ARELLANO
Issued 2/22/2024 APPLICANT
CofO in Progress 9/30/2024 JEFFREY BULL
Permit Finaled 4/23/2025 JOHN JANSON
CofO Issued 4/23/2025 JOHN JANSON
Permit Finaled 4/23/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/20/2023 RYAN KIM
Roof/Waste drainage to street Cleared 9/20/2023 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 9/21/2023 RYAN KIM
Sewer availability Cleared 9/21/2023 RYAN KIM
Construction near power lines Cleared 11/27/2023 OSCAR CASTRO
Low Impact Development (LID) Cleared 2/14/2024 LUIS LUVANO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/7/2024 Approved JEFFREY BULL
PLUMBING-Rough 3/11/2024 Approved JEFFREY BULL
Excavation/Setback/Form/Re-Bar 3/12/2024 Approved JEFFREY BULL
Footing/Foundation/Slab 3/12/2024 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 3/29/2024 Partial Approval SEAN WIRCH
BUILDING-Rough-Frame 4/4/2024 Not Ready for Inspection JEFFREY BULL
ELECTRICAL-Rough 4/4/2024 Approved JEFFREY BULL
Green Building Rough 4/4/2024 Not Ready for Inspection JEFFREY BULL
PLUMBING-Rough 4/4/2024 Approved JEFFREY BULL
Rough-Elec/Plmb/HVAC 4/4/2024 Approved JEFFREY BULL
Shower Pan 4/4/2024 Approved JEFFREY BULL
Verify Sprinkler Sign Off 4/4/2024 Approved JEFFREY BULL
Insulation 4/9/2024 Approved JEFFREY BULL
Drywall Nailing 4/23/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 8/12/2024 Approved JEFFREY BULL
Final 8/12/2024 Corrections Issued JEFFREY BULL
Green Building Final 8/12/2024 Not Ready for Inspection JEFFREY BULL
Green Building Rough 8/12/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 8/12/2024 SGSOV Approved JEFFREY BULL
Service/Power Release 8/12/2024 Not Ready for Inspection JEFFREY BULL
Smoke Detectors 8/12/2024 Approved JEFFREY BULL
Final 9/12/2024 Not Ready for Inspection JEFFREY BULL
Green Building Final 9/12/2024 Approved JEFFREY BULL
Final 9/30/2024 OK to Issue CofO JEFFREY BULL
Service/Power Release 9/30/2024 Approved JEFFREY BULL