12789 N ADELPHIA AVE 91340

Certificate Information: 12789 N ADELPHIA AVE 91340

Application / Permit
23014-20000-03427
Plan Check / Job No.
B23VN11484
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD TO & CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK PER WFPP.
Permit Issued
Issued on 9/12/2023
Issuing Office
Valley
Current Status
CofO Issued on 7/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2023 APPLICANT
Assigned to Plan Check Engineer 8/31/2023 JESSE ARELLANO
Corrections Issued 9/2/2023 JESSE ARELLANO
Building Plans Picked Up 9/7/2023 APPLICANT
Plan Check Approved 9/12/2023 ISIS ARGUETA
Issued 9/12/2023 APPLICANT
CofO in Progress 6/26/2025 KEVIN BERBERYAN
Permit Finaled 7/1/2025 RUBEN SALAS
CofO Issued 7/1/2025 RUBEN SALAS
Permit Finaled 7/1/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/8/2023 JOHN LIN
Roof/Waste drainage to street Cleared 9/8/2023 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 9/12/2023 JOHN LIN
Sewer availability Cleared 9/12/2023 JOHN LIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 10/30/2023 Approved KEVIN BERBERYAN
Underground Mechanical 10/30/2023 Approved KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 11/2/2023 Approved KEVIN BERBERYAN
Footing/Foundation/Slab 11/2/2023 Approved KEVIN BERBERYAN
Gas Test 11/8/2023 Approved KEVIN BERBERYAN
Underground Mechanical 11/8/2023 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 11/17/2023 Partial Approval KEVIN BERBERYAN
ELECTRICAL-Rough 11/17/2023 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 11/17/2023 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 11/22/2023 Conditional Approval KEVIN BERBERYAN
ELECTRICAL-Rough 11/22/2023 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 11/22/2023 Approved KEVIN BERBERYAN
PLUMBING-Rough 11/22/2023 Approved KEVIN BERBERYAN
HVAC-Rough 12/1/2023 Approved KEVIN BERBERYAN
Insulation 12/1/2023 Approved KEVIN BERBERYAN
Drywall Nailing 12/5/2023 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 12/5/2023 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 2/12/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 2/12/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 2/12/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 2/12/2024 Approved CHRISTOPHER ROJAS
MERV13>=Final 2/12/2024 Approved CHRISTOPHER ROJAS
MERV13>=Rough 2/12/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Final 2/12/2024 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 2/12/2024 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 2/12/2024 Approved CHRISTOPHER ROJAS
Final 3/5/2024 Corrections Issued KEVIN BERBERYAN
HVAC-Final 3/5/2024 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 3/5/2024 SGSOV Approved KEVIN BERBERYAN
Final 3/8/2024 OK to Issue CofO KEVIN BERBERYAN