17166 W KINGSBURY ST 91344
Certificate Information: 17166 W KINGSBURY ST 91344
- Application / Permit
- 23014-20000-03415
- Plan Check / Job No.
- B23VN11441
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. NEW ADDITION TO EXISTING ACCESSORY DWELLING UNIT per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 9/25/2023
- Issuing Office
- Current Status
- CofO Issued on 12/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2023 | EDWIN ESPIN |
| Corrections Issued | 8/31/2023 | EDWIN ESPIN |
| Plan Check Approved | 9/19/2023 | JOHNPAUL ISIP |
| Issued | 9/25/2023 | APPLICANT |
| CofO in Progress | 11/6/2024 | JAVIER RAMOS JR |
| Permit Finaled | 12/17/2024 | RUBEN SALAS |
| CofO Issued | 12/17/2024 | RUBEN SALAS |
| Permit Finaled | 12/17/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/12/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2023 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 9/14/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/15/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen,, Scott; Lic. No.: NA37989 | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/26/2023 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 12/14/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/27/2024 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2024 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 6/27/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 6/27/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 7/11/2024 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 7/23/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/31/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 7/31/2024 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 7/31/2024 | Approved | JAVIER RAMOS JR |
| Shower Pan | 8/15/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/29/2024 | Approved | JAVIER RAMOS JR |
| Final | 10/31/2024 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 10/31/2024 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 10/31/2024 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 10/31/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 11/5/2024 | OK to Issue CofO | JAVIER RAMOS JR |
| Smoke Detectors | 11/5/2024 | Approved | JAVIER RAMOS JR |