14400 W TYLER ST 91342
Certificate Information: 14400 W TYLER ST 91342
- Application / Permit
- 23014-20000-03375
- Plan Check / Job No.
- B23VN11276
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 30' 10" X 36'10" SIX CARS GARAGE AT THE FRONT OF SFD AND ADD 56'1" X 55'1" TWO STORY ADDITION AT THE BACK SIDE OF THE SFD, NFPA-13D FIRE SPRINKLERS THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 2/29/2024
- Issuing Office
- Current Status
- Issued on 2/29/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2023 | RARES BODEA |
| Corrections Issued | 9/5/2023 | RARES BODEA |
| Quality Review Completed | 9/7/2023 | STEVEN KIM |
| Applicant returned to address corrections | 10/25/2023 | RARES BODEA |
| Applicant returned to address corrections | 11/7/2023 | RARES BODEA |
| Plan Check Approved | 2/20/2024 | RARES BODEA |
| Issued | 2/29/2024 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 11/21/2023 | SAMUEL LINN |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2023 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 12/5/2023 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 12/13/2023 | EDGAR ALCARAZ |
Contact Information
| Architect | Liu,, Siyuan; Lic. No.: C39404 | 1701 NAVARRO AVE PASADENA, CA 91103 |
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/29/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 4/1/2024 | Corrections Issued | KEVIN BERBERYAN |
| Pre-Inspection | 4/1/2024 | Partial Inspection | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 4/3/2024 | Partial Approval | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 4/3/2024 | Partial Approval | KEVIN BERBERYAN |
| Sewer | 4/3/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Underground Mechanical | 4/3/2024 | Approved | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 4/23/2024 | Partial Approval | KEVIN BERBERYAN |
| Wood Frame | 5/7/2024 | Corrections Issued | KEVIN BERBERYAN |
| Deputy Wood Construction | 5/16/2024 | Conditional Approval | ROBERT GOLD |
| Wood Frame | 5/17/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Wood Frame | 5/21/2024 | Corrections Issued | JOHN COLEMAN |
| Wood Frame | 5/23/2024 | Corrections Issued | KEVIN BERBERYAN |
| Deputy Drilled-In Anchors | 5/29/2024 | Approved | KEVIN BERBERYAN |
| Wood Frame | 5/29/2024 | Partial Approval | KEVIN BERBERYAN |
| Wood Frame | 7/17/2024 | Corrections Issued | KEVIN BERBERYAN |
| Deputy Wood Construction | 8/6/2024 | Conditional Approval | ROBERT GOLD |
| HVAC-Rough | 9/17/2024 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 9/17/2024 | Corrections Issued | KEVIN BERBERYAN |
| Sewer | 9/17/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Wood Frame | 9/17/2024 | Corrections Issued | KEVIN BERBERYAN |
| Wood Frame | 9/24/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 9/27/2024 | Partial Approval | KEVIN BERBERYAN |
| Green Building Rough | 9/27/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 10/22/2024 | Corrections Issued | KEVIN BERBERYAN |
| HVAC-Rough | 10/22/2024 | Partial Approval | KEVIN BERBERYAN |
| PLUMBING-Rough | 10/22/2024 | Corrections Issued | KEVIN BERBERYAN |
| Sewer | 10/22/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 11/18/2024 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 11/18/2024 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 11/18/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| Sewer | 11/18/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 11/19/2024 | Partial Approval | KEVIN BERBERYAN |
| Green Building Rough | 11/19/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| PLUMBING-Rough | 11/19/2024 | Partial Approval | KEVIN BERBERYAN |
| Drywall Nailing | 1/27/2025 | Partial Approval | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 1/27/2025 | Corrections Issued | KEVIN BERBERYAN |
| Wood Frame | 1/27/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 1/30/2025 | Approved | KEVIN BERBERYAN |
| Insulation | 2/10/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 2/13/2025 | Conditional Approval | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 2/26/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 2/26/2025 | Corrections Issued | LOUIS ESCOTO |
| Green Building Rough | 2/26/2025 | Approved | LOUIS ESCOTO |
| Insulation | 2/26/2025 | Approved | LOUIS ESCOTO |
| Verify Sprinkler Sign Off | 2/26/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 2/28/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 2/28/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 6/16/2025 | Approved | KEVIN BERBERYAN |
| Final | 6/16/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 6/16/2025 | Approved | KEVIN BERBERYAN |
| Green Building Final | 6/16/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 6/16/2025 | SGSOV Not Ready | KEVIN BERBERYAN |
| Smoke Detectors | 6/16/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 6/27/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Final | 6/27/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 6/27/2025 | SGSOV Not Ready | KEVIN BERBERYAN |
| Smoke Detectors | 6/27/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| ELECTRICAL-Final | 7/29/2025 | Corrections Issued | KEVIN BERBERYAN |
| Final | 7/29/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 7/29/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Final | 7/29/2025 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Final | 7/29/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 7/29/2025 | SGSOV Not Ready | KEVIN BERBERYAN |
| Smoke Detectors | 7/29/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 1/28/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Final | 1/28/2026 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 1/28/2026 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 1/28/2026 | Approved | KEVIN BERBERYAN |