225 1/4-1/2 W 85TH ST 90003

Certificate Information: 225 1/4-1/2 W 85TH ST 90003

Application / Permit
23014-20000-03369
Plan Check / Job No.
B23VN11267
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE AND (N) ADDITION TO 2 (N) ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c)1, (d)1, and (g)
Permit Issued
Issued on 9/30/2023
Issuing Office
Current Status
CofO Issued on 4/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2023 APPLICANT
Assigned to Plan Check Engineer 8/25/2023 ISIS ARGUETA
Corrections Issued 8/28/2023 ISIS ARGUETA
Plan Check Approved 9/13/2023 CARLOS MONTES
Issued 9/30/2023 APPLICANT
CofO in Progress 4/11/2024 MICHAEL LEWIS
Permit Finaled 4/16/2024 DEROLD HAUFF
Permit Finaled 4/16/2024 DEROLD HAUFF
CofO Issued 4/16/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/6/2023 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 9/6/2023 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 9/7/2023 CHRISTINA BRACO
Sewer availability Cleared 9/7/2023 CHRISTINA BRACO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/26/2023 Not Ready for Inspection MICHAEL LEWIS
Deputy Drilled-In Anchors 10/30/2023 Conditional Approval MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 10/31/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 10/31/2023 Approved MICHAEL LEWIS
Underground Mechanical 10/31/2023 Approved MICHAEL LEWIS
ELECTRICAL-Rough 11/30/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/30/2023 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 11/30/2023 Approved MICHAEL LEWIS
Insulation 12/6/2023 Partial Approval MICHAEL LEWIS
BUILDING-Rough-Frame 12/8/2023 Approved MICHAEL LEWIS
Green Building Rough 12/8/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 12/8/2023 Approved MICHAEL LEWIS
Insulation 12/12/2023 Conditional Approval MICHAEL LEWIS
Drywall Nailing 12/28/2023 Corrections Issued MICHAEL LEWIS
Drywall Nailing 1/4/2024 Not Ready for Inspection SABAS ALONSO
Drywall Nailing 1/9/2024 Partial Inspection MICHAEL LEWIS
Insulation 1/9/2024 Partial Inspection MICHAEL LEWIS
Interior/Exterior Lathing 1/9/2024 Approved MICHAEL LEWIS
Shower Pan 1/9/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 2/20/2024 SGSOV Not Ready MICHAEL LEWIS
Final 2/23/2024 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 2/23/2024 SGSOV Not Ready MICHAEL LEWIS
Sewer 2/23/2024 Approved MICHAEL LEWIS
Underground Mechanical 2/23/2024 Approved MICHAEL LEWIS
Final 3/8/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 3/8/2024 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 3/8/2024 SGSOV Not Ready MICHAEL LEWIS
Smoke Detectors 3/8/2024 Corrections Issued MICHAEL LEWIS
Final 3/13/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 3/18/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 3/18/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 3/18/2024 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 3/18/2024 Approved MICHAEL LEWIS
Final 3/20/2024 Partial Inspection MICHAEL LEWIS
Final 4/10/2024 OK to Issue CofO MICHAEL LEWIS
Service/Power Release 4/11/2024 Approved MICHAEL LEWIS