9931 N RUFFNER AVE 91343

Certificate Information: 9931 N RUFFNER AVE 91343

Application / Permit
23014-20000-03366
Plan Check / Job No.
B23VN11262
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan POPOSED 16'X29' (464 SF) REC ROOM ADDITION TO (E) SFD
Permit Issued
Issued on 2/8/2024
Issuing Office
Current Status
CofO Issued on 2/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2023 APPLICANT
Assigned to Plan Check Engineer 8/24/2023 JAD BASMA
Corrections Issued 8/27/2023 JAD BASMA
Quality Review Completed 10/5/2023 PRANITA SHAH
Applicant returned to address corrections 11/3/2023 JAD BASMA
Applicant returned to address corrections 1/16/2024 JAD BASMA
Plan Check Approved 1/23/2024 JAD BASMA
Issued 2/8/2024 APPLICANT
CofO in Progress 1/22/2025 JAVIER RAMOS JR
Permit Finaled 2/27/2025 RUBEN SALAS
CofO Issued 2/27/2025 RUBEN SALAS
Permit Finaled 2/27/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/18/2023 TAL SHEMEN
Roof/Waste drainage to street Cleared 9/18/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 9/20/2023 TAL SHEMEN
Sewer availability Cleared 9/20/2023 TAL SHEMEN
Grading Pre-Inspection Cleared 10/16/2023 MICHAEL TEMPLE
Senate Bill 9 Cleared 10/24/2023 NATHAN ROMINE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/18/2024 Approved JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 5/2/2024 Not Ready for Inspection JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 5/14/2024 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 5/17/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/30/2024 Partial Inspection JAVIER RAMOS JR
PLUMBING-Rough 5/30/2024 Partial Inspection JAVIER RAMOS JR
Pre-Inspection 5/30/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/24/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 6/24/2024 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 8/6/2024 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 8/6/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Approved JAVIER RAMOS JR
HVAC-Rough 8/6/2024 Partial Inspection JAVIER RAMOS JR
PLUMBING-Rough 8/6/2024 Approved JAVIER RAMOS JR
HVAC-Rough 8/9/2024 Approved JAVIER RAMOS JR
Insulation 8/9/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 8/9/2024 Partial Approval JAVIER RAMOS JR
Drywall Nailing 8/12/2024 Approved LOUIS ESCOTO
Interior/Exterior Lathing 8/12/2024 Not Ready for Inspection LOUIS ESCOTO
Pre-Inspection 8/16/2024 Approved JAVIER RAMOS JR
Final 12/20/2024 No Access for Inspection RAUL OLAGI
BUILDING-Rough-Frame 12/27/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 12/27/2024 Not Ready for Inspection JAVIER RAMOS JR
Final 12/27/2024 Not Ready for Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 12/27/2024 Approved JAVIER RAMOS JR
Green Building Final 12/27/2024 Approved JAVIER RAMOS JR
Green Building Rough 12/27/2024 Approved JAVIER RAMOS JR
HVAC-Final 12/27/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 12/27/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/27/2024 SGSOV Not Ready JAVIER RAMOS JR
Smoke Detectors 12/27/2024 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Final 12/31/2024 Approved JAVIER RAMOS JR
Smoke Detectors 12/31/2024 Partial Inspection JAVIER RAMOS JR
Final 1/13/2025 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 1/13/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 1/13/2025 Corrections Issued JAVIER RAMOS JR
Final 1/21/2025 OK to Issue CofO JAVIER RAMOS JR
Smoke Detectors 1/21/2025 Approved JAVIER RAMOS JR