5513 N COSTELLO AVE 91401

Certificate Information: 5513 N COSTELLO AVE 91401

Application / Permit
23014-20000-03359
Plan Check / Job No.
B23VN11245
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ALL (E) INT. & EXT. WALLS EXCEPT PORTION OF THE FRONT WALL, AND ERECT AN IRR. SHAPED 47'-7" x 56'-11" TWO-STORY SINGLE FAMILY DWELLING WITH ATT. 2-CAR GARAGE; NFPA-13D THRU-OUT
Permit Issued
Issued on 3/22/2024
Issuing Office
Valley
Current Status
CofO Issued on 8/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2023 APPLICANT
Assigned to Plan Check Engineer 8/24/2023 SEAN SHAHMIRI
Corrections Issued 8/28/2023 SEAN SHAHMIRI
Quality Review Completed 8/28/2023 OMID HEDAYAT
Building Plans Picked Up 8/29/2023 APPLICANT
Applicant returned to address corrections 11/29/2023 SEAN SHAHMIRI
Applicant returned to address corrections 12/11/2023 SEAN SHAHMIRI
Plan Check Approved 12/20/2023 SEAN SHAHMIRI
Issued 3/22/2024 APPLICANT
CofO in Progress 8/8/2025 RYAN SALAZAR
Permit Finaled 8/14/2025 RUBEN SALAS
CofO Issued 8/14/2025 RUBEN SALAS
Permit Finaled 8/14/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/29/2023 LEE GUILBEAUX
Permit Cleared 8/29/2023 LEE GUILBEAUX
Sewer availability Cleared 8/29/2023 LEE GUILBEAUX
Low Impact Development (LID) Cleared 11/6/2023 SHAHIN KHAZEY
Roof/Waste drainage to street Cleared 12/5/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/13/2024 Partial Approval JAVIER RAMOS JR
Special/Order Compliance 5/13/2024 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 5/16/2024 Partial Approval RYAN SALAZAR
Deputy Reinf. Concrete 5/17/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 6/4/2024 Approved JOHN COLEMAN
Deputy Reinf. Concrete 6/6/2024 Conditional Approval ROBERT GOLD
Deputy Steel/Welding 6/21/2024 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 7/5/2024 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 8/7/2024 Partial Approval RYAN SALAZAR
Green Building Rough 8/7/2024 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Rough 9/19/2024 Approved JENNIFER RABUCHIN
Gas Test 9/19/2024 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 9/19/2024 Approved JENNIFER RABUCHIN
HVAC-Rough 9/25/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 10/1/2024 Approved RYAN SALAZAR
Deputy Wood Construction 10/1/2024 Conditional Approval RAUL OLAGI
Green Building Rough 10/1/2024 Approved RYAN SALAZAR
Underground Mechanical 10/1/2024 Approved RYAN SALAZAR
Insulation 10/17/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 10/21/2024 Approved GAREN HAYRAPETYAN
Drywall Nailing 10/23/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 10/23/2024 Partial Approval RYAN SALAZAR
Interior/Exterior Lathing 11/1/2024 Not Ready for Inspection RYAN SALAZAR
Shower Pan 11/1/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/25/2024 Approved RYAN SALAZAR
ELECTRICAL-Final 12/10/2024 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Final 1/6/2025 Approved RYAN SALAZAR
Service/Power Release 1/6/2025 Approved RYAN SALAZAR
Gas Test 4/30/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 4/30/2025 SGSOV Approved RYAN SALAZAR
Final 6/18/2025 Partial Approval RYAN SALAZAR
Green Building Final 6/18/2025 Approved RYAN SALAZAR
Smoke Detectors 6/18/2025 Approved RYAN SALAZAR
Final 8/7/2025 OK to Issue CofO RYAN SALAZAR