9271-9273 N GREENBUSH AVE 91331
Certificate Information: 9271-9273 N GREENBUSH AVE 91331
- Application / Permit
- 23014-20000-03358
- Plan Check / Job No.
- B23VN11244
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 35'-7" X 22'-0" ADDITION TO & CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e).
- Permit Issued
- Issued on 9/22/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 8/26/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 9/1/2023 | APPLICANT |
| Plan Check Approved | 9/22/2023 | ROSENDO MEDINA |
| Issued | 9/22/2023 | APPLICANT |
| CofO in Progress | 7/9/2024 | GREGG CUMMINGS |
| CofO Issued | 7/22/2024 | RUBEN SALAS |
| Permit Finaled | 7/22/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/6/2023 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 9/6/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 9/13/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Papazyan,, Andranik; Lic. No.: C56824 | 635 W COLORADO ST STE 104 GLENDALE, CA 91204 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/16/2024 | Corrections Issued | GREGG CUMMINGS |
| Underground Mechanical | 4/19/2024 | Partial Approval | KIRK SANDERS |
| Deputy Drilled-In Anchors | 4/25/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 4/25/2024 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 4/30/2024 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 4/30/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 5/28/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2024 | Partial Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/28/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/30/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 5/30/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/3/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Green Building Rough | 6/3/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Insulation | 6/3/2024 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/5/2024 | Approved | GREGG CUMMINGS |
| Green Building Rough | 6/5/2024 | Approved | GREGG CUMMINGS |
| Insulation | 6/5/2024 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 6/7/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 6/7/2024 | Approved | GREGG CUMMINGS |
| Shower Pan | 6/7/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 6/24/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 6/27/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 6/27/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 6/27/2024 | Approved | GREGG CUMMINGS |
| HVAC-Final | 6/27/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 6/27/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 6/27/2024 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 6/27/2024 | Approved | GREGG CUMMINGS |
| Final | 7/2/2024 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Final | 7/5/2024 | Approved | GREGG CUMMINGS |
| Final | 7/5/2024 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 7/5/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 7/5/2024 | Approved | GREGG CUMMINGS |
| Service/Power Release | 7/5/2024 | Approved | GREGG CUMMINGS |