14811 W TUPPER ST 91402
Certificate Information: 14811 W TUPPER ST 91402
- Application / Permit
- 23014-20000-03354
- Plan Check / Job No.
- B23VN11232
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN New 1,121 SF ADU attached to Existing 2-Car Garage PER LAMC 12.22 A.33(c)(d) WORK DONE PER WFPP
- Permit Issued
- Issued on 11/14/2023
- Issuing Office
- Current Status
- CofO Issued on 4/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2023 | KHUONG TRUONG |
| Corrections Issued | 9/1/2023 | KHUONG TRUONG |
| Applicant returned to address corrections | 9/27/2023 | KHUONG TRUONG |
| Applicant returned to address corrections | 11/9/2023 | KHUONG TRUONG |
| Plan Check Approved | 11/13/2023 | KHUONG TRUONG |
| Issued | 11/14/2023 | APPLICANT |
| CofO in Progress | 4/3/2024 | JENNIFER RABUCHIN |
| No Progress | 4/8/2024 | ROBERT GOLD |
| CofO in Progress | 4/8/2024 | ROBERT GOLD |
| Permit Finaled | 4/11/2024 | RUBEN SALAS |
| CofO Issued | 4/11/2024 | RUBEN SALAS |
| Permit Finaled | 4/11/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/30/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/2/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/2/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 11/2/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 11/6/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/29/2023 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/29/2023 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 11/29/2023 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 11/29/2023 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 12/4/2023 | Corrections Issued | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 12/7/2023 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2023 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/9/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/9/2024 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 1/9/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 1/9/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/9/2024 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/9/2024 | Approved | JENNIFER RABUCHIN |
| Insulation | 1/16/2024 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 1/16/2024 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 1/22/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/22/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/15/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 3/15/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 3/15/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 3/15/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 3/15/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Final | 3/15/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 3/15/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 3/15/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 3/15/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 3/15/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/3/2024 | Approved | JENNIFER RABUCHIN |
| Final | 4/3/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 4/3/2024 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 4/3/2024 | Approved | JENNIFER RABUCHIN |