8944 N GEYSER AVE 91324

Certificate Information: 8944 N GEYSER AVE 91324

Application / Permit
23014-20000-03351
Plan Check / Job No.
B23VN11222
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
11'-6" x 7'-0" ADDITION TO THE SINGLE FAMILY DWELLING - WORK PER WFPP.
Permit Issued
Issued on 8/25/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2023 APPLICANT
Assigned to Plan Check Engineer 8/21/2023 ISIS ARGUETA
Corrections Issued 8/21/2023 ISIS ARGUETA
Issued 8/25/2023 APPLICANT
CofO in Progress 5/8/2025 DAVID SCANTLIN
Permit Finaled 4/4/2026 MICHAEL PELHAM
CofO Issued 4/4/2026 MICHAEL PELHAM
Permit Finaled 4/4/2026 MICHAEL PELHAM

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/24/2023 TAL SHEMEN
Roof/Waste drainage to street Cleared 8/24/2023 TAL SHEMEN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/31/2024 Approved KRISTEN CAUSEY
PLUMBING-Rough 6/18/2024 Partial Approval KRISTEN CAUSEY
BUILDING-Rough-Frame 7/22/2024 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 7/22/2024 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 10/17/2024 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 10/17/2024 Partial Approval KRISTEN CAUSEY
Interior/Exterior Lathing 10/31/2024 Approved KRISTEN CAUSEY
ELECTRICAL-Rough 12/2/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 12/16/2024 Approved DAVID SCANTLIN
Drywall Nailing 12/16/2024 Approved DAVID SCANTLIN
Insulation 12/16/2024 Approved DAVID SCANTLIN
Final 4/25/2025 Corrections Issued KRISTEN CAUSEY
Smoke Detectors 4/25/2025 Approved KRISTEN CAUSEY
ELECTRICAL-Final 5/8/2025 Approved DAVID SCANTLIN
Final 5/8/2025 OK to Issue CofO DAVID SCANTLIN
HVAC-Final 5/8/2025 Approved DAVID SCANTLIN
PLUMBING-Final 5/8/2025 Approved DAVID SCANTLIN