6843 N MATILIJA AVE 91405

Certificate Information: 6843 N MATILIJA AVE 91405

Application / Permit
23014-20000-03324
Plan Check / Job No.
B23VN11151
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan: Addition and Remodel to (E) 1-Story SFD w/Attached Garage
Permit Issued
Issued on 10/31/2023
Issuing Office
Current Status
CofO Issued on 9/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/20/2023 APPLICANT
Assigned to Plan Check Engineer 8/22/2023 DAVID CASTILLO
Corrections Issued 8/23/2023 DAVID CASTILLO
Applicant returned to address corrections 9/13/2023 DAVID CASTILLO
Applicant returned to address corrections 10/21/2023 DAVID CASTILLO
Plan Check Approved 10/24/2023 DAVID CASTILLO
Issued 10/31/2023 APPLICANT
CofO in Progress 9/4/2024 RYAN SALAZAR
Permit Finaled 9/12/2024 DANIEL ORRANTE
CofO Issued 9/12/2024 DANIEL ORRANTE
Permit Finaled 9/12/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/1/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/18/2023 CARLOS AGUILERA

Contact Information

Contractor D & M Renovation Brothers; Lic. No.: 1086977-B       ,
Engineer Lobnan,, Essam; Lic. No.: C78053 PO BOX 64373      LOS ANGELES, CA 90064

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/25/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 4/30/2024 Partial Approval RYAN SALAZAR
PLUMBING-Rough 4/30/2024 Partial Approval RYAN SALAZAR
Underground Mechanical 4/30/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 5/1/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 5/10/2024 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 5/24/2024 Approved RYAN SALAZAR
HVAC-Rough 5/24/2024 Approved RYAN SALAZAR
PLUMBING-Rough 5/24/2024 Approved RYAN SALAZAR
Insulation 6/3/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 6/3/2024 Partial Approval RYAN SALAZAR
Shower Pan 6/3/2024 Approved RYAN SALAZAR
Drywall Nailing 6/17/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/17/2024 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 6/18/2024 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 8/29/2024 Approved RYAN SALAZAR
Final 8/29/2024 Corrections Issued RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 8/29/2024 SGSOV Approved RYAN SALAZAR
Smoke Detectors 8/29/2024 Approved RYAN SALAZAR
Final 9/4/2024 OK to Issue CofO RYAN SALAZAR