6843 N MATILIJA AVE 91405
Certificate Information: 6843 N MATILIJA AVE 91405
- Application / Permit
- 23014-20000-03324
- Plan Check / Job No.
- B23VN11151
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan: Addition and Remodel to (E) 1-Story SFD w/Attached Garage
- Permit Issued
- Issued on 10/31/2023
- Issuing Office
- Current Status
- CofO Issued on 9/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2023 | DAVID CASTILLO |
| Corrections Issued | 8/23/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 9/13/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 10/21/2023 | DAVID CASTILLO |
| Plan Check Approved | 10/24/2023 | DAVID CASTILLO |
| Issued | 10/31/2023 | APPLICANT |
| CofO in Progress | 9/4/2024 | RYAN SALAZAR |
| Permit Finaled | 9/12/2024 | DANIEL ORRANTE |
| CofO Issued | 9/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/1/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | D & M Renovation Brothers; Lic. No.: 1086977-B | , |
| Engineer | Lobnan,, Essam; Lic. No.: C78053 | PO BOX 64373 LOS ANGELES, CA 90064 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/25/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2024 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 4/30/2024 | Partial Approval | RYAN SALAZAR |
| Underground Mechanical | 4/30/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2024 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 5/24/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 5/24/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 5/24/2024 | Approved | RYAN SALAZAR |
| Insulation | 6/3/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 6/3/2024 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 6/3/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 6/17/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/17/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/18/2024 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 8/29/2024 | Approved | RYAN SALAZAR |
| Final | 8/29/2024 | Corrections Issued | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 8/29/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 8/29/2024 | Approved | RYAN SALAZAR |
| Final | 9/4/2024 | OK to Issue CofO | RYAN SALAZAR |