22703-22705 W BURTON ST 91304
Certificate Information: 22703-22705 W BURTON ST 91304
- Application / Permit
- 23014-20000-03322
- Plan Check / Job No.
- B23VN11147
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan: Addition for Attached ADU (411 SF) to (E) 1-Story SFD w/ Attached Garage per LAMC 12.22 A.33(c) and (e), per engrs calcs
- Permit Issued
- Issued on 10/17/2023
- Issuing Office
- Current Status
- CofO Issued on 2/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2023 | AMY GUEVARRA |
| Corrections Issued | 8/23/2023 | AMY GUEVARRA |
| Applicant returned to address corrections | 8/31/2023 | AMY GUEVARRA |
| Applicant returned to address corrections | 9/7/2023 | DAVID CASTILLO |
| Plan Check Approved | 9/14/2023 | DAVID CASTILLO |
| Issued | 10/17/2023 | APPLICANT |
| CofO in Progress | 2/21/2024 | JEFFREY HARTLINE |
| Permit Finaled | 2/29/2024 | JOHN JANSON |
| CofO Issued | 2/29/2024 | JOHN JANSON |
| Permit Finaled | 2/29/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/25/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2023 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 8/25/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/25/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Montoya'S General Contractor Inc; Lic. No.: 1017138-B | , |
| Engineer | Loayza,, Miguel Antonio; Lic. No.: NA26290 | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/1/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 11/6/2023 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 11/6/2023 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/12/2023 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2023 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 12/12/2023 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 12/12/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Wood Frame | 12/18/2023 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 12/21/2023 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 12/21/2023 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 12/21/2023 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 12/21/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 12/26/2023 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 12/26/2023 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 1/4/2024 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 1/4/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 2/13/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 2/13/2024 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 2/13/2024 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 2/13/2024 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 2/13/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 2/16/2024 | OK to Issue CofO | JEFFREY HARTLINE |
| Service/Power Release | 2/16/2024 | Approved | JEFFREY HARTLINE |
| Service/Power Release | 2/28/2024 | Approved | JEFFREY HARTLINE |
| Service/Power Release | 2/29/2024 | Approved | JEFFREY HARTLINE |