12616 W GILMORE ST 91606
Certificate Information: 12616 W GILMORE ST 91606
- Application / Permit
- 23014-20000-03290
- Plan Check / Job No.
- B23VN11030
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE AND (N) 16'-0" x 27'-2" ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). "COMPLY WITH DEPARTMENT ORDER effective date 08/18/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 12/29/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2023 | KAMYAR EMAMI |
| Corrections Issued | 8/23/2023 | KAMYAR EMAMI |
| Building Plans Picked Up | 8/25/2023 | APPLICANT |
| Plan Check Approved | 12/21/2023 | ISIS ARGUETA |
| Issued | 12/29/2023 | APPLICANT |
| CofO in Progress | 4/11/2025 | OGANES TARAKHCHYAN |
| Permit Finaled | 4/11/2025 | RUBEN SALAS |
| CofO Issued | 4/11/2025 | RUBEN SALAS |
| Permit Finaled | 4/11/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/26/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 8/26/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/26/2023 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 11/4/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/26/2024 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 2/26/2024 | Corrections Issued | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 2/28/2024 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 3/12/2024 | No Access for Inspection | JOSE AVILA |
| PLUMBING-Rough | 3/14/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 4/5/2024 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 4/5/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 5/6/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Rough | 5/6/2024 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 5/6/2024 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 5/13/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/13/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 5/13/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 5/13/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/13/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/22/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 6/5/2024 | Not Ready for Inspection | JOSE AVILA |
| HVAC-Rough | 6/5/2024 | Not Ready for Inspection | JOSE AVILA |
| PLUMBING-Rough | 6/5/2024 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 6/10/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 6/10/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 6/10/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 6/17/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Rough | 6/17/2024 | No Access for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/27/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/10/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/16/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 7/16/2024 | Approved | VINCENT HANLEY |
| Insulation | 7/23/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 7/23/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Insulation | 8/13/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/13/2024 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 8/23/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 3/27/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 3/27/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Final | 3/27/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 3/27/2025 | SGSOV Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 3/27/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 4/4/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 4/4/2025 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 4/4/2025 | Approved | OGANES TARAKHCHYAN |