4512 N BEN AVE 91607
Certificate Information: 4512 N BEN AVE 91607
- Application / Permit
- 23014-20000-03281
- Plan Check / Job No.
- B23VN10996
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND ADDITION TO MAKE A 2- STORY 61'4"X63'0" SINGLE FAMILY DWELLING WITH AN ATTACHED GARAGE. 61'4" PORTION OF WALL ON THE NORTH SIDE OF THE BUILDING TO REMAIN. NFPA 13 D FIRE SPRINKLER REQUIRED THROUGHOUT.
- Permit Issued
- Issued on 3/20/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2023 | MARVEL DELACRUZ |
| Corrections Issued | 9/6/2023 | MARVEL DELACRUZ |
| Quality Review Completed | 9/8/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 9/13/2023 | APPLICANT |
| Applicant returned to address corrections | 1/3/2024 | MARVEL DELACRUZ |
| Plan Check Approved | 3/15/2024 | MARVEL DELACRUZ |
| Issued | 3/20/2024 | APPLICANT |
| CofO in Progress | 6/12/2025 | MISAEL ESPARZA |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
| CofO Issued | 7/8/2025 | RUBEN SALAS |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| ZI | Cleared | 11/2/2023 | STEVEN WECHSLER |
| Low Impact Development (LID) | Cleared | 11/21/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 11/27/2023 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/28/2023 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 12/14/2023 | CARLOS RAMIREZ |
Contact Information
| Architect | Lee,, Kenneth David; Lic. No.: C10141 | 16501 ACADEMIA DRIVE ENCINO, CA 91436 |
| Contractor | A R M Builders Inc; Lic. No.: 915352-B | 1080 S LA CIENEGA #311 LOS ANGELES, CA 90035 |
| Engineer | Shakiban,, George; Lic. No.: C39908 | 23945 CALABASAS RD STE 101 CALABASAS, CA 91302 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/15/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 5/20/2024 | Partial Approval | MISAEL ESPARZA |
| Underground Mechanical | 6/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 6/12/2024 | Partial Approval | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 6/14/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Deputy Reinf. Concrete | 6/18/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 6/20/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 8/2/2024 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 8/2/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Insulation | 8/8/2024 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2024 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 11/4/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Green Building Rough | 11/4/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| MERV13>=Rough | 11/4/2024 | Approved | CHRISTOPHER ROJAS |
| Deputy Wood Construction | 11/5/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 11/18/2024 | Not Ready for Inspection | DAVID MATSON |
| HVAC-Rough | 11/18/2024 | Corrections Issued | DAVID MATSON |
| Rough-Elec/Plmb/HVAC | 11/18/2024 | Not Ready for Inspection | DAVID MATSON |
| ELECTRICAL-Rough | 11/22/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 11/22/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/6/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 12/6/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 12/6/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 12/6/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 12/9/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/19/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Shower Pan | 12/19/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/27/2024 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 12/27/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/30/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Insulation | 12/31/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 1/14/2025 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 1/17/2025 | Approved | CHRISTOPHER ROJAS |
| Sewer | 5/7/2025 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 5/7/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 5/14/2025 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 5/14/2025 | Approved | JAVIER RAMOS JR |
| Gas Test | 5/16/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 5/16/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 5/16/2025 | SGSOV Approved | JAVIER RAMOS JR |
| HVAC-Final | 5/19/2025 | Approved | JAVIER RAMOS JR |
| Final | 5/30/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 5/30/2025 | Approved | JAVIER RAMOS JR |
| MERV13>=Final | 5/30/2025 | Approved | JAVIER RAMOS JR |
| Final | 6/11/2025 | OK to Issue CofO | MISAEL ESPARZA |