5505-5507 N VANALDEN AVE 91356
Certificate Information: 5505-5507 N VANALDEN AVE 91356
- Application / Permit
- 23014-20000-03275
- Plan Check / Job No.
- B23VN10973
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) 2202 SF SFD EXCEPT FOR 12'-7" OF WALL AND FOUNDATION. REBUILD 96'-11" X 82'-5" IRREGULAR SHAPED 1-STORY SFD W/ ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 12/12/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2023 | RAPHAEL ROSAS |
| Corrections Issued | 8/22/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 8/23/2023 | STEVEN KIM |
| Building Plans Picked Up | 8/24/2023 | APPLICANT |
| Applicant returned to address corrections | 9/11/2023 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 10/23/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 11/2/2023 | RAPHAEL ROSAS |
| Issued | 12/12/2023 | APPLICANT |
| CofO in Progress | 1/17/2025 | JOHN KIDWELL |
| Permit Finaled | 3/4/2025 | JOHN JANSON |
| CofO Issued | 3/4/2025 | JOHN JANSON |
| Permit Finaled | 3/4/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/26/2023 | CARLOS AGUILERA |
| Permit | Cleared | 8/26/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/29/2023 | CARLOS AGUILERA |
| Trees in Parkway | Cleared | 9/28/2023 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 10/23/2023 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 10/27/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 11/1/2023 | NIKKI ZULUETA |
| GPI Written Notices | Cleared | 11/2/2023 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 11/2/2023 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khansa,, Eyass; Lic. No.: C91758 | 2252 JOSIE AVE LONG BEACH, CA 90815 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/31/2024 | Approved | JOHN KIDWELL |
| Footing/Foundation/Slab | 2/14/2024 | Corrections Issued | JOHN KIDWELL |
| Deputy Wood Construction | 3/8/2024 | Corrections Issued | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2024 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 3/28/2024 | Partial Inspection | JOHN KIDWELL |
| HVAC-Rough | 3/28/2024 | Partial Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 3/28/2024 | Partial Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 4/2/2024 | Partial Inspection | JOHN KIDWELL |
| HVAC-Rough | 4/2/2024 | Partial Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 4/2/2024 | Partial Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 4/10/2024 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 4/10/2024 | Approved | JOHN KIDWELL |
| Green Building Rough | 4/10/2024 | Approved | JOHN KIDWELL |
| HVAC-Rough | 4/10/2024 | Approved | JOHN KIDWELL |
| MERV13>=Rough | 4/10/2024 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 4/10/2024 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 4/26/2024 | Approved | JOHN KIDWELL |
| Insulation | 4/26/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Interior/Exterior Lathing | 4/26/2024 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 5/8/2024 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 5/8/2024 | Approved | JOHN KIDWELL |
| Shower Pan | 5/8/2024 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 5/8/2024 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 8/28/2024 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Final | 9/5/2024 | Approved | JOHN KIDWELL |
| Service/Power Release | 9/12/2024 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 11/15/2024 | Approved | JOHN KIDWELL |
| Final | 12/10/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 12/10/2024 | Approved | JOHN KIDWELL |
| Green Building Final | 12/10/2024 | Not Ready for Inspection | JOHN KIDWELL |
| MERV13>=Final | 12/10/2024 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 12/10/2024 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 12/10/2024 | Approved | JOHN KIDWELL |
| Final | 12/18/2024 | Corrections Issued | JOHN KIDWELL |
| Green Building Final | 12/18/2024 | Approved | JOHN KIDWELL |
| Final | 1/17/2025 | OK to Issue CofO | JOHN KIDWELL |