7905 N BEN AVE 91605
Certificate Information: 7905 N BEN AVE 91605
- Application / Permit
- 23014-20000-03272
- Plan Check / Job No.
- B23VN10952
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Addition and major remodel to existing 1-story S.F.D and new attached lattice patio
- Permit Issued
- Issued on 3/8/2024
- Issuing Office
- Current Status
- CofO Issued on 8/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2023 | HOOMAN HAJIZADEH |
| Corrections Issued | 9/7/2023 | HOOMAN HAJIZADEH |
| Quality Review Completed | 9/7/2023 | KAVIAN REFAHI |
| Applicant returned to address corrections | 1/19/2024 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 2/9/2024 | HOOMAN HAJIZADEH |
| Plan Check Approved | 3/6/2024 | HOOMAN HAJIZADEH |
| Issued | 3/8/2024 | APPLICANT |
| CofO in Progress | 8/18/2025 | MATTHEW NELSON |
| Permit Finaled | 8/26/2025 | RUBEN SALAS |
| CofO Issued | 8/26/2025 | RUBEN SALAS |
| Permit Finaled | 8/26/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/9/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/12/2023 | CARLOS AGUILERA |
| Senate Bill 9 | Cleared | 9/28/2023 | BRENNEN OBETO |
| Miscellaneous | Cleared | 12/21/2023 | SUSAN WONG |
| Low Impact Development (LID) | Cleared | 12/27/2023 | TRISH PARAS |
| Roof/Waste drainage to street | Cleared | 1/5/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazarians,, Harmick; Lic. No.: C91232 | 9825 OSO AVE CHATSWORTH, CA 91311 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/22/2024 | Partial Inspection | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 6/18/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 6/26/2024 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2024 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 7/15/2024 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 7/18/2024 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2024 | Approved | MATTHEW NELSON |
| Deputy Wood Construction | 8/20/2024 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 8/22/2024 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2024 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/4/2024 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 10/4/2024 | Approved | MATTHEW NELSON |
| Gas Test | 10/4/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 10/4/2024 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 10/4/2024 | Approved | MATTHEW NELSON |
| Wood Frame | 10/4/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/8/2024 | Corrections Issued | MATTHEW NELSON |
| HVAC-Rough | 10/8/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/10/2024 | Approved | MATTHEW NELSON |
| Insulation | 10/17/2024 | Approved | MATTHEW NELSON |
| Shower Pan | 10/17/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 10/25/2024 | Partial Approval | MATTHEW NELSON |
| Interior/Exterior Lathing | 10/25/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 11/27/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 8/8/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 8/8/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 8/8/2025 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 8/8/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 8/15/2025 | OK to Issue CofO | MATTHEW NELSON |