7905 N BEN AVE 91605

Certificate Information: 7905 N BEN AVE 91605

Application / Permit
23014-20000-03272
Plan Check / Job No.
B23VN10952
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Addition and major remodel to existing 1-story S.F.D and new attached lattice patio
Permit Issued
Issued on 3/8/2024
Issuing Office
Current Status
CofO Issued on 8/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/18/2023 APPLICANT
Assigned to Plan Check Engineer 8/31/2023 HOOMAN HAJIZADEH
Corrections Issued 9/7/2023 HOOMAN HAJIZADEH
Quality Review Completed 9/7/2023 KAVIAN REFAHI
Applicant returned to address corrections 1/19/2024 HOOMAN HAJIZADEH
Applicant returned to address corrections 2/9/2024 HOOMAN HAJIZADEH
Plan Check Approved 3/6/2024 HOOMAN HAJIZADEH
Issued 3/8/2024 APPLICANT
CofO in Progress 8/18/2025 MATTHEW NELSON
Permit Finaled 8/26/2025 RUBEN SALAS
CofO Issued 8/26/2025 RUBEN SALAS
Permit Finaled 8/26/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/9/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/12/2023 CARLOS AGUILERA
Sewer availability Cleared 9/12/2023 CARLOS AGUILERA
Senate Bill 9 Cleared 9/28/2023 BRENNEN OBETO
Miscellaneous Cleared 12/21/2023 SUSAN WONG
Low Impact Development (LID) Cleared 12/27/2023 TRISH PARAS
Roof/Waste drainage to street Cleared 1/5/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Nazarians,, Harmick; Lic. No.: C91232 9825 OSO AVE      CHATSWORTH, CA 91311

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/22/2024 Partial Inspection MATTHEW NELSON
Deputy Drilled-In Anchors 6/18/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 6/26/2024 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 7/15/2024 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 7/18/2024 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 7/26/2024 Approved MATTHEW NELSON
Deputy Wood Construction 8/20/2024 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 8/22/2024 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 8/22/2024 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 10/4/2024 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 10/4/2024 Approved MATTHEW NELSON
Gas Test 10/4/2024 Approved MATTHEW NELSON
HVAC-Rough 10/4/2024 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 10/4/2024 Approved MATTHEW NELSON
Wood Frame 10/4/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 10/8/2024 Corrections Issued MATTHEW NELSON
HVAC-Rough 10/8/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 10/10/2024 Approved MATTHEW NELSON
Insulation 10/17/2024 Approved MATTHEW NELSON
Shower Pan 10/17/2024 Approved MATTHEW NELSON
Drywall Nailing 10/25/2024 Partial Approval MATTHEW NELSON
Interior/Exterior Lathing 10/25/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 11/27/2024 Approved MATTHEW NELSON
Drywall Nailing 8/8/2025 Approved NICHOLAS TROWBRIDGE
Final 8/8/2025 Corrections Issued NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 8/8/2025 SGSOV Approved NICHOLAS TROWBRIDGE
Smoke Detectors 8/8/2025 Approved NICHOLAS TROWBRIDGE
Final 8/15/2025 OK to Issue CofO MATTHEW NELSON