13616 W EMELITA ST 91401

Certificate Information: 13616 W EMELITA ST 91401

Application / Permit
23014-20000-03259
Plan Check / Job No.
B23VN10919
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20'3" X 20'3" DETACHED GARAGE AND (N) 20'8" X 20' ADDITION TO (N) ACCESSORY DWELLING UNIT (765 SF). WORK TO BE DONE PER WFPP AND ENGINEER DETAIL.
Permit Issued
Issued on 8/31/2023
Issuing Office
Current Status
CofO Issued on 4/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2023 APPLICANT
Assigned to Plan Check Engineer 8/18/2023 SERGIO MUNIZ
Corrections Issued 8/21/2023 SERGIO MUNIZ
Building Plans Picked Up 8/22/2023 APPLICANT
Plan Check Approved 8/24/2023 MADISON ODELL
Issued 8/31/2023 APPLICANT
CofO in Progress 4/11/2024 RYAN SALAZAR
Permit Finaled 4/16/2024 RUBEN SALAS
CofO Issued 4/16/2024 RUBEN SALAS
Permit Finaled 4/16/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/22/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 8/22/2023 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 8/22/2023 ROMAN GUTIERREZ
Sewer availability Cleared 8/22/2023 ROMAN GUTIERREZ
ZA Case Cleared 8/24/2023 ASHLEY RODARTE

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/18/2023 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 9/18/2023 Partial Approval RYAN SALAZAR
Sewer 9/18/2023 Not Ready for Inspection RYAN SALAZAR
Deputy Drilled-In Anchors 9/20/2023 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 9/21/2023 Approved RYAN SALAZAR
Underground Mechanical 9/21/2023 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 10/2/2023 Partial Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 11/20/2023 Approved RYAN SALAZAR
Wood Frame 11/20/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 12/18/2023 Partial Approval RYAN SALAZAR
Special/Order Compliance 12/18/2023 Corrections Issued RYAN SALAZAR
ELECTRICAL-Rough 1/4/2024 Approved RYAN SALAZAR
HVAC-Rough 1/4/2024 Approved RYAN SALAZAR
PLUMBING-Rough 1/4/2024 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 1/10/2024 Approved DAVID MATSON
Shower Pan 1/10/2024 Not Ready for Inspection DAVID MATSON
Insulation 1/29/2024 Not Ready for Inspection DAVID MATSON
Shower Pan 1/29/2024 Approved DAVID MATSON
BUILDING-Rough-Frame 2/1/2024 Approved RYAN SALAZAR
Green Building Rough 2/1/2024 Approved RYAN SALAZAR
Insulation 2/1/2024 Approved RYAN SALAZAR
Drywall Nailing 2/6/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 2/6/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 4/5/2024 SGSOV Not Ready RYAN SALAZAR
Final 4/10/2024 OK to Issue CofO RYAN SALAZAR
Green Building Final 4/10/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 4/10/2024 SGSOV Approved RYAN SALAZAR
Service/Power Release 4/10/2024 Approved RYAN SALAZAR
Smoke Detectors 4/10/2024 Approved RYAN SALAZAR