1543 N BENEDICT CANYON DR 90210

Certificate Information: 1543 N BENEDICT CANYON DR 90210

Application / Permit
23014-20000-03251
Plan Check / Job No.
B23VN10880
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
14'X6' AND 13'X16' ADDTION TO (E) SINGLE FAMILY DWELLING. WORK PER ENGINEERING
Permit Issued
Issued on 9/5/2023
Issuing Office
Valley
Current Status
CofO Issued on 10/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2023 APPLICANT
Assigned to Plan Check Engineer 8/18/2023 SERGIO MUNIZ
Corrections Issued 8/21/2023 SERGIO MUNIZ
Building Plans Picked Up 8/22/2023 APPLICANT
Issued 9/5/2023 APPLICANT
CofO in Progress 9/22/2025 SEAN HAUPT
Permit Finaled 10/22/2025 RICHARD STEINBACH
CofO Issued 10/22/2025 RICHARD STEINBACH
Permit Finaled 10/22/2025 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/29/2023 JASON NG
Eng Process Fee Ord 176,300 Cleared 8/30/2023 JASON NG
Grading Pre-Inspection Cleared 8/31/2023 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,
Engineer Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 1171 JUSTIN AVE APT 3      GLENDALE, CA 91201

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/8/2024 Partial Approval SEAN HAUPT
Deputy Drilled-In Anchors 4/22/2024 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 4/24/2024 Approved SEAN HAUPT
Footing/Foundation/Slab 4/24/2024 Approved SEAN HAUPT
PLUMBING-Rough 5/8/2024 Corrections Issued SEAN HAUPT
Wood Frame 5/8/2024 Approved SEAN HAUPT
BUILDING-Rough-Frame 8/27/2024 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Rough 8/27/2024 Not Ready for Inspection SEAN HAUPT
Green Building Rough 8/27/2024 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 8/27/2024 Corrections Issued SEAN HAUPT
PLUMBING-Rough 8/29/2024 Partial Approval SEAN HAUPT
ELECTRICAL-Rough 9/5/2024 Corrections Issued SEAN HAUPT
PLUMBING-Rough 9/5/2024 Corrections Issued SEAN HAUPT
BUILDING-Rough-Frame 11/5/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 11/5/2024 Not Ready for Inspection STEPHANIE SWANSON
Green Building Rough 11/5/2024 Not Ready for Inspection STEPHANIE SWANSON
Interior/Exterior Lathing 11/5/2024 Not Ready for Inspection STEPHANIE SWANSON
PLUMBING-Rough 11/5/2024 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 11/26/2024 Approved SEAN HAUPT
ELECTRICAL-Rough 11/26/2024 Approved SEAN HAUPT
Green Building Rough 11/26/2024 Approved SEAN HAUPT
Interior/Exterior Lathing 11/26/2024 Approved SEAN HAUPT
Insulation 12/31/2024 Approved SEAN HAUPT
Drywall Nailing 1/15/2025 Approved REGINA MENDEZ
Final 8/29/2025 Corrections Issued SEAN HAUPT
Green Building Final 8/29/2025 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 8/29/2025 SGSOV Not Ready SEAN HAUPT
Smoke Detectors 8/29/2025 Approved SEAN HAUPT
Final 9/17/2025 Not Ready for Inspection SEAN HAUPT
Green Building Final 9/17/2025 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 9/17/2025 SGSOV Not Ready SEAN HAUPT
Final 9/19/2025 OK to Issue CofO SEAN HAUPT
Green Building Final 9/19/2025 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 9/19/2025 SGSOV Approved SEAN HAUPT