11020 N HERRICK AVE 91331
Certificate Information: 11020 N HERRICK AVE 91331
- Application / Permit
- 23014-20000-03249
- Plan Check / Job No.
- B23VN10865
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan 130SF New addition to Existing House, (2 New bathroom) WORK DONE PER WFPP
- Permit Issued
- Issued on 9/7/2023
- Issuing Office
- Current Status
- CofO Issued on 7/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2023 | ZAW HAN |
| Corrections Issued | 8/20/2023 | ZAW HAN |
| Plan Check Approved | 9/1/2023 | KHUONG TRUONG |
| Issued | 9/7/2023 | APPLICANT |
| CofO in Progress | 7/9/2024 | MICHEL ABAJAN |
| Permit Finaled | 7/19/2024 | RUBEN SALAS |
| CofO Issued | 7/19/2024 | RUBEN SALAS |
| Permit Finaled | 7/19/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2023 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 8/22/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/22/2023 | DAGOVERTO GUERRERO |
| Clean Up Green Up | Cleared | 8/24/2023 | BRENNEN OBETO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/11/2023 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 10/6/2023 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 10/6/2023 | Partial Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/1/2023 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 11/1/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| METHANE-Rough | 11/1/2023 | Partial Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 11/1/2023 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2023 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 12/21/2023 | Partial Inspection | MICHEL ABAJAN |
| METHANE-Rough | 12/21/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 1/12/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 1/12/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 1/12/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/22/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 1/22/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 1/22/2024 | Approved | MICHEL ABAJAN |
| Insulation | 2/15/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 2/21/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/8/2024 | Approved | MICHEL ABAJAN |
| Final | 7/8/2024 | OK to Issue CofO | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/8/2024 | Approved | MICHEL ABAJAN |
| Green Building Final | 7/8/2024 | Approved | MICHEL ABAJAN |
| HVAC-Final | 7/8/2024 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 7/8/2024 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 7/8/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/8/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/8/2024 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 7/8/2024 | Approved | MICHEL ABAJAN |