11020 N HERRICK AVE 91331

Certificate Information: 11020 N HERRICK AVE 91331

Application / Permit
23014-20000-03249
Plan Check / Job No.
B23VN10865
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan 130SF New addition to Existing House, (2 New bathroom) WORK DONE PER WFPP
Permit Issued
Issued on 9/7/2023
Issuing Office
Current Status
CofO Issued on 7/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2023 APPLICANT
Assigned to Plan Check Engineer 8/18/2023 ZAW HAN
Corrections Issued 8/20/2023 ZAW HAN
Plan Check Approved 9/1/2023 KHUONG TRUONG
Issued 9/7/2023 APPLICANT
CofO in Progress 7/9/2024 MICHEL ABAJAN
Permit Finaled 7/19/2024 RUBEN SALAS
CofO Issued 7/19/2024 RUBEN SALAS
Permit Finaled 7/19/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/22/2023 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 8/22/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 8/22/2023 DAGOVERTO GUERRERO
Clean Up Green Up Cleared 8/24/2023 BRENNEN OBETO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/11/2023 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 10/6/2023 Approved MICHEL ABAJAN
Pre-Inspection 10/6/2023 Partial Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 11/1/2023 Partial Approval JUAN VALENZUELA
Green Building Rough 11/1/2023 Not Ready for Inspection JUAN VALENZUELA
METHANE-Rough 11/1/2023 Partial Inspection JUAN VALENZUELA
PLUMBING-Rough 11/1/2023 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/21/2023 Partial Approval MICHEL ABAJAN
Green Building Rough 12/21/2023 Partial Inspection MICHEL ABAJAN
METHANE-Rough 12/21/2023 Approved MICHEL ABAJAN
ELECTRICAL-Rough 1/12/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/12/2024 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 1/12/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 1/22/2024 Approved MICHEL ABAJAN
Green Building Rough 1/22/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/22/2024 Approved MICHEL ABAJAN
Insulation 2/15/2024 Approved MICHEL ABAJAN
Drywall Nailing 2/21/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 7/8/2024 Approved MICHEL ABAJAN
Final 7/8/2024 OK to Issue CofO MICHEL ABAJAN
Footing/Foundation/Slab 7/8/2024 Approved MICHEL ABAJAN
Green Building Final 7/8/2024 Approved MICHEL ABAJAN
HVAC-Final 7/8/2024 Approved MICHEL ABAJAN
METHANE-Barrier 7/8/2024 Approved MICHEL ABAJAN
METHANE-Subgrade 7/8/2024 Approved MICHEL ABAJAN
PLUMBING-Final 7/8/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/8/2024 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 7/8/2024 Approved MICHEL ABAJAN