2431 N WILD OAK DR 90068
Certificate Information: 2431 N WILD OAK DR 90068
- Application / Permit
- 23014-20000-03248
- Plan Check / Job No.
- B23VN10855
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL PERMIT TO 22016-20000-30436. REVISE WORK DESCRIPTION TO: 22'-8" X 3'-6" ADDITION UNDER EX. ROOF OVERHANG TO EXPAND KITCHEN AND REMODEL. REMOVE INTERIOR DROPPED CEILING FOR VAULTED CEILING. REMOVE EXT. POSTS. NEW ENGINEER OF RECORD.
- Permit Issued
- Issued on 11/14/2023
- Issuing Office
- Metro
- Current Status
- Issued on 11/14/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2023 | HAYATO TSUCHIYA |
| Corrections Issued | 8/19/2023 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 8/22/2023 | APPLICANT |
| Applicant returned to address corrections | 9/7/2023 | ROSENDO MEDINA |
| Plan Check Approved | 9/12/2023 | ALEC MOUSAKHANIAN |
| Issued | 11/14/2023 | APPLICANT |
Permit Application Clearance Information
| "D" conditions | Cleared | 9/8/2023 | DANALYNN DOMINGUEZ |
| ZI | Cleared | 9/8/2023 | DANALYNN DOMINGUEZ |
Contact Information
| Contractor | Westmont Design And Construction; Lic. No.: 836202-B | 409 UNDERHILL DRIVE GLENDORA, CA 91741 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/16/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 11/20/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 2/20/2024 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 2/20/2024 | Partial Approval | ROY SPAULDING |
| Green Building Rough | 2/20/2024 | Approved | ROY SPAULDING |
| HVAC-Rough | 2/20/2024 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 2/20/2024 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 2/27/2024 | Approved | ROY SPAULDING |
| Insulation | 2/29/2024 | Approved | ROY SPAULDING |
| Deputy Wood Construction | 3/6/2024 | Conditional Approval | ROY SPAULDING |
| Drywall Nailing | 3/7/2024 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 3/7/2024 | Approved | ROY SPAULDING |