4926 N SANCOLA AVE 91601

Certificate Information: 4926 N SANCOLA AVE 91601

Application / Permit
23014-20000-03247
Plan Check / Job No.
B23VN10852
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert and addition to existing (16' x 19') 1-story detached garage to ADU (25' x 19') per LAMC 12.22 A.33 (c) and (d). NFPA 13D Fire Sprinklers Throughout.
Permit Issued
Issued on 12/1/2023
Issuing Office
Current Status
CofO Issued on 2/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2023 APPLICANT
Assigned to Plan Check Engineer 8/17/2023 VAHAN JIVALAGIAN
Corrections Issued 8/24/2023 VAHAN JIVALAGIAN
Quality Review Completed 8/24/2023 OMID HEDAYAT
Building Plans Picked Up 8/25/2023 APPLICANT
Applicant returned to address corrections 11/22/2023 VAHAN JIVALAGIAN
Applicant returned to address corrections 11/28/2023 VAHAN JIVALAGIAN
Plan Check Approved 11/30/2023 VAHAN JIVALAGIAN
Issued 12/1/2023 APPLICANT
CofO in Progress 2/7/2025 ROBERTO PALACIOS-LOPEZ
Permit Finaled 2/12/2025 RUBEN SALAS
CofO Issued 2/12/2025 RUBEN SALAS
Permit Finaled 2/12/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/29/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 8/29/2023 TAL SHEMEN
Roof/Waste drainage to street Cleared 8/29/2023 TAL SHEMEN
Sewer availability Cleared 8/29/2023 TAL SHEMEN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/21/2024 Partial Approval JOHN HAYES
Excavation/Setback/Form/Re-Bar 6/20/2024 Corrections Issued JOSE AVILA
PLUMBING-Rough 6/20/2024 Approved JOSE AVILA
Footing/Foundation/Slab 6/24/2024 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 7/15/2024 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 7/19/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 8/6/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Rough 8/6/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/7/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 8/7/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 8/7/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 8/7/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Shower Pan 8/14/2024 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 8/14/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 8/16/2024 Corrections Issued JOSE AVILA
HVAC-Rough 8/16/2024 Corrections Issued JOSE AVILA
PLUMBING-Rough 8/16/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 8/21/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 8/21/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 8/21/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 8/21/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 8/30/2024 Approved JOSE AVILA
Drywall Nailing 9/9/2024 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 12/20/2024 Corrections Issued JOSE AVILA
HVAC-Final 12/20/2024 Corrections Issued JOSE AVILA
PLUMBING-Final 12/20/2024 Conditional Approval JOSE AVILA
Final 1/27/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 1/27/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 1/27/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 1/27/2025 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 1/31/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 2/7/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 2/7/2025 SGSOV Approved ROBERTO PALACIOS-LOPEZ