4926 N SANCOLA AVE 91601
Certificate Information: 4926 N SANCOLA AVE 91601
- Application / Permit
- 23014-20000-03247
- Plan Check / Job No.
- B23VN10852
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert and addition to existing (16' x 19') 1-story detached garage to ADU (25' x 19') per LAMC 12.22 A.33 (c) and (d). NFPA 13D Fire Sprinklers Throughout.
- Permit Issued
- Issued on 12/1/2023
- Issuing Office
- Current Status
- CofO Issued on 2/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2023 | VAHAN JIVALAGIAN |
| Corrections Issued | 8/24/2023 | VAHAN JIVALAGIAN |
| Quality Review Completed | 8/24/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 8/25/2023 | APPLICANT |
| Applicant returned to address corrections | 11/22/2023 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 11/28/2023 | VAHAN JIVALAGIAN |
| Plan Check Approved | 11/30/2023 | VAHAN JIVALAGIAN |
| Issued | 12/1/2023 | APPLICANT |
| CofO in Progress | 2/7/2025 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 2/12/2025 | RUBEN SALAS |
| CofO Issued | 2/12/2025 | RUBEN SALAS |
| Permit Finaled | 2/12/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/29/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2023 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 8/29/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 8/29/2023 | TAL SHEMEN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/21/2024 | Partial Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 6/20/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 6/20/2024 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 6/24/2024 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/15/2024 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 7/19/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 8/6/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 8/6/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 8/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 8/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 8/14/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 8/14/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 8/16/2024 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 8/16/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 8/16/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 8/21/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 8/21/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 8/21/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 8/21/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 8/30/2024 | Approved | JOSE AVILA |
| Drywall Nailing | 9/9/2024 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 12/20/2024 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 12/20/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 12/20/2024 | Conditional Approval | JOSE AVILA |
| Final | 1/27/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 1/27/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 1/27/2025 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 1/27/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 1/31/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 2/7/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/7/2025 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |