22702 W HAMLIN ST 91307

Certificate Information: 22702 W HAMLIN ST 91307

Application / Permit
23014-20000-03239
Plan Check / Job No.
B23VN10817
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN CONVERT (E) DETACHED GARAGE WITH 18'-8" X 21'-4" ADDITION TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). **SEE COMMENTS**
Permit Issued
Issued on 12/14/2023
Issuing Office
Current Status
CofO Issued on 5/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2023 APPLICANT
Assigned to Plan Check Engineer 8/17/2023 ALEC MOUSAKHANIAN
Corrections Issued 8/18/2023 ALEC MOUSAKHANIAN
Plan Check Approved 12/13/2023 ALEC MOUSAKHANIAN
Issued 12/14/2023 APPLICANT
CofO in Progress 5/2/2024 TROY SANDERS
Permit Finaled 5/20/2024 JOHN JANSON
CofO Issued 5/20/2024 JOHN JANSON
Permit Finaled 5/20/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/24/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 8/24/2023 TAL SHEMEN
Roof/Waste drainage to street Cleared 8/24/2023 TAL SHEMEN
Sewer availability Cleared 8/24/2023 TAL SHEMEN
Construction near power lines Cleared 12/5/2023 RIDWAN HARDY

Contact Information

Contractor Value Construction Inc; Lic. No.: 982837-B       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/31/2024 Partial Approval TROY SANDERS
Excavation/Setback/Form/Re-Bar 2/15/2024 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/1/2024 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 3/13/2024 Partial Approval GEVORK IPCHYAN
ELECTRICAL-Rough 3/13/2024 Partial Approval GEVORK IPCHYAN
HVAC-Rough 3/13/2024 Approved GEVORK IPCHYAN
PLUMBING-Rough 3/13/2024 Approved GEVORK IPCHYAN
Shower Pan 3/15/2024 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 3/20/2024 Approved GEVORK IPCHYAN
Insulation 3/20/2024 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 3/20/2024 Approved GEVORK IPCHYAN
Drywall Nailing 3/26/2024 Approved GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/2/2024 Partial Approval TROY SANDERS
ELECTRICAL-Final 5/1/2024 Approved TROY SANDERS
Final 5/1/2024 OK to Issue CofO TROY SANDERS
Footing/Foundation/Slab 5/1/2024 Approved TROY SANDERS
HVAC-Final 5/1/2024 Approved TROY SANDERS
PLUMBING-Final 5/1/2024 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 5/1/2024 SGSOV Approved TROY SANDERS
Service/Power Release 5/1/2024 Approved TROY SANDERS
Smoke Detectors 5/1/2024 Approved TROY SANDERS