22702 W HAMLIN ST 91307
Certificate Information: 22702 W HAMLIN ST 91307
- Application / Permit
- 23014-20000-03239
- Plan Check / Job No.
- B23VN10817
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN CONVERT (E) DETACHED GARAGE WITH 18'-8" X 21'-4" ADDITION TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). **SEE COMMENTS**
- Permit Issued
- Issued on 12/14/2023
- Issuing Office
- Current Status
- CofO Issued on 5/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 8/18/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 12/13/2023 | ALEC MOUSAKHANIAN |
| Issued | 12/14/2023 | APPLICANT |
| CofO in Progress | 5/2/2024 | TROY SANDERS |
| Permit Finaled | 5/20/2024 | JOHN JANSON |
| CofO Issued | 5/20/2024 | JOHN JANSON |
| Permit Finaled | 5/20/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/24/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2023 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 8/24/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 8/24/2023 | TAL SHEMEN |
| Construction near power lines | Cleared | 12/5/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Value Construction Inc; Lic. No.: 982837-B | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/31/2024 | Partial Approval | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 2/15/2024 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2024 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 3/13/2024 | Partial Approval | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 3/13/2024 | Partial Approval | GEVORK IPCHYAN |
| HVAC-Rough | 3/13/2024 | Approved | GEVORK IPCHYAN |
| PLUMBING-Rough | 3/13/2024 | Approved | GEVORK IPCHYAN |
| Shower Pan | 3/15/2024 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 3/20/2024 | Approved | GEVORK IPCHYAN |
| Insulation | 3/20/2024 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 3/20/2024 | Approved | GEVORK IPCHYAN |
| Drywall Nailing | 3/26/2024 | Approved | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2024 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Final | 5/1/2024 | Approved | TROY SANDERS |
| Final | 5/1/2024 | OK to Issue CofO | TROY SANDERS |
| Footing/Foundation/Slab | 5/1/2024 | Approved | TROY SANDERS |
| HVAC-Final | 5/1/2024 | Approved | TROY SANDERS |
| PLUMBING-Final | 5/1/2024 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/1/2024 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 5/1/2024 | Approved | TROY SANDERS |
| Smoke Detectors | 5/1/2024 | Approved | TROY SANDERS |