14927-14929 W TITUS ST 91402

Certificate Information: 14927-14929 W TITUS ST 91402

Application / Permit
23014-20000-03237
Plan Check / Job No.
B23VN10806
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE (342 SQ. FT) AND PORTION OF SINGLE FAMILY DWELLING (148 SQ. FT.) TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22. ADD 24'-11" x 35'-4" IRREGULAR SHAPED ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e). WORK DONE PER WFPP.
Permit Issued
Issued on 10/3/2023
Issuing Office
Valley
Current Status
CofO Issued on 12/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2023 APPLICANT
Assigned to Plan Check Engineer 8/17/2023 JEROME MAGAT PALMA
Corrections Issued 8/17/2023 JEROME MAGAT PALMA
Building Plans Picked Up 8/21/2023 APPLICANT
Plan Check Approved 9/29/2023 GIOVANNY CHAVEZ
Issued 10/3/2023 APPLICANT
CofO in Progress 12/1/2024 VINCENT HANLEY
Permit Finaled 12/19/2024 RUBEN SALAS
CofO Issued 12/19/2024 RUBEN SALAS
Permit Finaled 12/19/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/30/2023 DAGOVERTO GUERRERO
Miscellaneous Cleared 8/31/2023 RYAN LY
Tract Map conditions Cleared 8/31/2023 RYAN LY
Eng Process Fee Ord 176,300 Cleared 9/5/2023 DAGOVERTO GUERRERO
Low Impact Development (LID) Cleared 9/21/2023 SHAHIN KHAZEY
Roof/Waste drainage to street Cleared 9/22/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 9/22/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/11/2023 Partial Approval CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 12/26/2023 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 12/29/2023 Corrections Issued GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 1/23/2024 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 1/23/2024 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 2/23/2024 Corrections Issued CHRISTOPHER ROJAS
HVAC-Rough 2/23/2024 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 2/23/2024 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 2/23/2024 Corrections Issued CHRISTOPHER ROJAS
Wood Frame 2/23/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/4/2024 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 4/4/2024 Approved MATTHEW NELSON
Green Building Rough 4/4/2024 Approved MATTHEW NELSON
HVAC-Rough 4/4/2024 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 4/4/2024 Approved MATTHEW NELSON
Wood Frame 4/4/2024 Not Ready for Inspection MATTHEW NELSON
HVAC-Final 4/8/2024 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 4/8/2024 Corrections Issued KIRK SANDERS
Wood Frame 4/8/2024 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 4/17/2024 Not Ready for Inspection DAVID ANDERSON
HVAC-Rough 4/17/2024 Approved DAVID ANDERSON
Insulation 4/17/2024 Corrections Issued DAVID ANDERSON
BUILDING-Rough-Frame 4/26/2024 Approved KIRK SANDERS
Footing/Foundation/Slab 4/26/2024 Approved KIRK SANDERS
Insulation 4/26/2024 Corrections Issued KIRK SANDERS
Shower Pan 4/26/2024 Approved KIRK SANDERS
Drywall Nailing 5/1/2024 Partial Approval GREGG CUMMINGS
Insulation 5/1/2024 Approved GREGG CUMMINGS
Interior/Exterior Lathing 5/1/2024 Partial Approval GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 9/10/2024 SGSOV Not Ready GREGG CUMMINGS
Pre-Inspection 9/12/2024 Corrections Issued VINCENT HANLEY
Final 10/9/2024 Corrections Issued VINCENT HANLEY
Green Building Final 10/9/2024 Approved VINCENT HANLEY
PLUMBING-Final 10/9/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 10/9/2024 SGSOV Approved VINCENT HANLEY
Service/Power Release 10/9/2024 Not Ready for Inspection VINCENT HANLEY
Smoke Detectors 10/9/2024 Approved VINCENT HANLEY
ELECTRICAL-Final 11/27/2024 Approved VINCENT HANLEY
Final 11/27/2024 OK to Issue CofO VINCENT HANLEY
HVAC-Final 11/27/2024 Approved VINCENT HANLEY
PLUMBING-Final 11/27/2024 Approved VINCENT HANLEY