19457 W FRIAR ST 91335

Certificate Information: 19457 W FRIAR ST 91335

Application / Permit
23014-20000-03236
Plan Check / Job No.
B23VN10805
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN CONVERT (E) DETACHED GARAGE TO ADU WITH ADDITION AND TRELLIS PER LAMC 12.22 A.33 (c) AND (d)
Permit Issued
Issued on 1/23/2024
Issuing Office
Current Status
CofO Issued on 6/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2023 APPLICANT
Assigned to Plan Check Engineer 8/17/2023 JOHNPAUL ISIP
Corrections Issued 8/18/2023 JOHNPAUL ISIP
Applicant returned to address corrections 12/14/2023 PINANK PATEL
Applicant returned to address corrections 12/22/2023 PINANK PATEL
Applicant returned to address corrections 12/27/2023 ALEC MOUSAKHANIAN
Plan Check Approved 1/20/2024 ALEC MOUSAKHANIAN
Issued 1/23/2024 APPLICANT
CofO in Progress 6/11/2024 ARUTYUN MADATYAN
Permit Finaled 6/21/2024 JOHN JANSON
CofO Issued 6/21/2024 JOHN JANSON
Permit Finaled 6/21/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/21/2023 DAGOVERTO GUERRERO
ZI Cleared 8/21/2023 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 8/22/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 8/22/2023 DAGOVERTO GUERRERO
Low Impact Development (LID) Cleared 8/28/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 8/28/2023 DAGOVERTO GUERRERO
Construction within easement Cleared 12/5/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/15/2024 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 2/15/2024 Partial Approval ARUTYUN MADATYAN
Excavation/Setback/Form/Re-Bar 2/23/2024 Partial Approval ARUTYUN MADATYAN
Footing/Foundation/Slab 2/26/2024 Partial Approval ARUTYUN MADATYAN
Underground Mechanical 2/26/2024 Not Ready for Inspection ARUTYUN MADATYAN
Deputy Drilled-In Anchors 2/29/2024 Partial Approval ARUTYUN MADATYAN
Footing/Foundation/Slab 2/29/2024 Approved ARUTYUN MADATYAN
Pre-Inspection 2/29/2024 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 3/11/2024 Partial Approval ARUTYUN MADATYAN
Green Building Rough 3/11/2024 Not Ready for Inspection ARUTYUN MADATYAN
Wood Frame 3/11/2024 Partial Approval ARUTYUN MADATYAN
PLUMBING-Rough 3/14/2024 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 3/18/2024 Approved ALEXANDER HANDY
HVAC-Rough 3/18/2024 Approved ALEXANDER HANDY
Shower Pan 3/19/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 3/21/2024 Corrections Issued ARUTYUN MADATYAN
Interior/Exterior Lathing 3/26/2024 Approved HORACE FULTZ
BUILDING-Rough-Frame 3/28/2024 Conditional Approval ARUTYUN MADATYAN
Green Building Rough 3/28/2024 Approved ARUTYUN MADATYAN
Insulation 3/29/2024 Approved HORACE FULTZ
Drywall Nailing 4/4/2024 Approved ALEXANDER HANDY
Sewer 4/8/2024 Approved ARUTYUN MADATYAN
Service/Power Release 5/17/2024 Corrections Issued ALEXANDER HANDY
PLUMBING-Final 5/20/2024 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 5/30/2024 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 5/30/2024 Not Ready for Inspection ARUTYUN MADATYAN
Final 5/30/2024 Corrections Issued ARUTYUN MADATYAN
Green Building Final 5/30/2024 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Final 5/30/2024 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 5/30/2024 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 5/30/2024 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 5/30/2024 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 6/4/2024 Approved ARUTYUN MADATYAN
Final 6/4/2024 Corrections Issued ARUTYUN MADATYAN
Green Building Final 6/4/2024 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Final 6/4/2024 Approved ARUTYUN MADATYAN
Service/Power Release 6/4/2024 Approved ARUTYUN MADATYAN
Final 6/11/2024 OK to Issue CofO ARUTYUN MADATYAN
Green Building Final 6/11/2024 Approved ARUTYUN MADATYAN