11746 W HARTSOOK ST 91607
Certificate Information: 11746 W HARTSOOK ST 91607
- Application / Permit
- 23014-20000-03231
- Plan Check / Job No.
- B23VN10790
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN 1. REMODEL EXISTING SECOND FLOOR. 2. CONVERT SECTION OF ATTIC SPACE INTO NEW LAUNDRY CLOSET AND BATHROOM - 103 SQ.FT. PER ENGINEERING DESIGN.
- Permit Issued
- Issued on 9/11/2023
- Issuing Office
- Current Status
- CofO Issued on 3/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2023 | ALFREDO JARA |
| Corrections Issued | 8/19/2023 | ALFREDO JARA |
| Plan Check Approved | 9/4/2023 | ALFREDO JARA |
| Issued | 9/11/2023 | APPLICANT |
| CofO in Progress | 1/15/2024 | CRAIG DAVIS |
| Permit Finaled | 3/27/2024 | DANIEL ORRANTE |
| CofO Issued | 3/27/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/27/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2023 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 8/22/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 8/22/2023 | ROMAN GUTIERREZ |
| Specific Plan | Cleared | 8/30/2023 | CHRISTIAN PEARSON |
| ZI | Cleared | 8/30/2023 | CHRISTIAN PEARSON |
| ZI | Cleared | 8/30/2023 | CHRISTIAN PEARSON |
Contact Information
| Contractor | Dream Remodeling Inc; Lic. No.: 889254-B | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/19/2023 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 10/2/2023 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 10/2/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Rough | 10/2/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 10/2/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Wood Frame | 10/2/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 10/11/2023 | Not Ready for Inspection | JOHN COLEMAN |
| ELECTRICAL-Rough | 10/11/2023 | Not Ready for Inspection | JOHN COLEMAN |
| HVAC-Rough | 10/11/2023 | Corrections Issued | JOHN COLEMAN |
| Interior/Exterior Lathing | 10/11/2023 | Partial Approval | JOHN COLEMAN |
| PLUMBING-Rough | 10/11/2023 | Approved | JOHN COLEMAN |
| Wood Frame | 10/11/2023 | Not Ready for Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 10/16/2023 | Partial Approval | JOHN COLEMAN |
| HVAC-Rough | 10/16/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Insulation | 10/16/2023 | Approved | JOHN COLEMAN |
| Shower Pan | 10/16/2023 | Approved | JOHN COLEMAN |
| Wood Frame | 10/16/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Drywall Nailing | 10/24/2023 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2023 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 10/24/2023 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/28/2023 | Approved | MISAEL ESPARZA |
| Final | 12/28/2023 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 12/28/2023 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 12/28/2023 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 1/12/2024 | Approved | CRAIG DAVIS |
| Final | 1/12/2024 | OK to Issue CofO | CRAIG DAVIS |
| HVAC-Final | 1/12/2024 | Approved | CRAIG DAVIS |
| PLUMBING-Final | 1/12/2024 | Approved | CRAIG DAVIS |