11746 W HARTSOOK ST 91607

Certificate Information: 11746 W HARTSOOK ST 91607

Application / Permit
23014-20000-03231
Plan Check / Job No.
B23VN10790
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN 1. REMODEL EXISTING SECOND FLOOR. 2. CONVERT SECTION OF ATTIC SPACE INTO NEW LAUNDRY CLOSET AND BATHROOM - 103 SQ.FT. PER ENGINEERING DESIGN.
Permit Issued
Issued on 9/11/2023
Issuing Office
Current Status
CofO Issued on 3/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2023 APPLICANT
Assigned to Plan Check Engineer 8/18/2023 ALFREDO JARA
Corrections Issued 8/19/2023 ALFREDO JARA
Plan Check Approved 9/4/2023 ALFREDO JARA
Issued 9/11/2023 APPLICANT
CofO in Progress 1/15/2024 CRAIG DAVIS
Permit Finaled 3/27/2024 DANIEL ORRANTE
CofO Issued 3/27/2024 DANIEL ORRANTE
Permit Finaled 3/27/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/22/2023 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 8/22/2023 ROMAN GUTIERREZ
Sewer availability Cleared 8/22/2023 ROMAN GUTIERREZ
Specific Plan Cleared 8/30/2023 CHRISTIAN PEARSON
ZI Cleared 8/30/2023 CHRISTIAN PEARSON
ZI Cleared 8/30/2023 CHRISTIAN PEARSON

Contact Information

Contractor Dream Remodeling Inc; Lic. No.: 889254-B       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/19/2023 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 10/2/2023 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 10/2/2023 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 10/2/2023 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 10/2/2023 Not Ready for Inspection JUAN VALENZUELA
Wood Frame 10/2/2023 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 10/11/2023 Not Ready for Inspection JOHN COLEMAN
ELECTRICAL-Rough 10/11/2023 Not Ready for Inspection JOHN COLEMAN
HVAC-Rough 10/11/2023 Corrections Issued JOHN COLEMAN
Interior/Exterior Lathing 10/11/2023 Partial Approval JOHN COLEMAN
PLUMBING-Rough 10/11/2023 Approved JOHN COLEMAN
Wood Frame 10/11/2023 Not Ready for Inspection JOHN COLEMAN
BUILDING-Rough-Frame 10/16/2023 Partial Approval JOHN COLEMAN
HVAC-Rough 10/16/2023 Not Ready for Inspection JOHN COLEMAN
Insulation 10/16/2023 Approved JOHN COLEMAN
Shower Pan 10/16/2023 Approved JOHN COLEMAN
Wood Frame 10/16/2023 Not Ready for Inspection JOHN COLEMAN
Drywall Nailing 10/24/2023 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 10/24/2023 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 12/28/2023 Approved MISAEL ESPARZA
Final 12/28/2023 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 12/28/2023 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 12/28/2023 Approved MISAEL ESPARZA
ELECTRICAL-Final 1/12/2024 Approved CRAIG DAVIS
Final 1/12/2024 OK to Issue CofO CRAIG DAVIS
HVAC-Final 1/12/2024 Approved CRAIG DAVIS
PLUMBING-Final 1/12/2024 Approved CRAIG DAVIS