900 S WESTHOLME AVE 90024
Certificate Information: 900 S WESTHOLME AVE 90024
- Application / Permit
- 23014-20000-03230
- Plan Check / Job No.
- B23VN10786
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 21'6" X 2'4" 1ST FLOOR ADDITION TO (E) SFD TO EXTEND THE LIVING ROOM AND ADD NEW POWDER ROOM , NEW 5'8" X 33'1" 2ND FLOOR ADDITION TO EXTEND BATHROOM , BEDROOM AND NEW W.I.C., REMODEL TO (E) SFD TO REMODEL LIVING ROOM , DINING ROOM , FAMILY ROOM , KITCHED , BATHROOMS , LAUNDRY AT 1ST FLOOR, REMODEL (3) BEDROOMS , (1) BATHROOM AT 2ND FLOOR , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 1/9/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2023 | RARES BODEA |
| Corrections Issued | 8/22/2023 | RARES BODEA |
| Quality Review Completed | 8/25/2023 | STEVEN KIM |
| Building Plans Picked Up | 8/25/2023 | APPLICANT |
| Applicant returned to address corrections | 10/26/2023 | RARES BODEA |
| Applicant returned to address corrections | 11/22/2023 | RARES BODEA |
| Plan Check Approved | 1/5/2024 | RARES BODEA |
| Issued | 1/9/2024 | APPLICANT |
| CofO in Progress | 11/7/2024 | STEPHANIE SWANSON |
| Permit Finaled | 11/12/2024 | RICHARD STEINBACH |
| CofO Issued | 11/12/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/12/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 9/18/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2023 | DARIN LAM |
| ZA Case | Cleared | 9/21/2023 | STEVEN WECHSLER |
| Roof/Waste drainage to street | Cleared | 9/26/2023 | DARIN LAM |
| Grading Pre-Inspection | Cleared | 10/26/2023 | RARES BODEA |
| Specific Plan | Cleared | 11/1/2023 | JOSHUA JONES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lerner,, George; Lic. No.: C40288 | 4668 WILLIS AVE SHERMAN OAKS, CA 91403 |
| Engineer | Salehipour,, Sassan A; Lic. No.: GE2579 | 1290 N LAKE AVENUE #204 PASADENA, CA 91104 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/10/2024 | Partial Inspection | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 1/19/2024 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 1/24/2024 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2024 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 3/7/2024 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 3/8/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Drilled-In Anchors | 3/28/2024 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2024 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 3/28/2024 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 4/10/2024 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2024 | Corrections Issued | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 5/1/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 5/1/2024 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2024 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2024 | Partial Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 5/6/2024 | Partial Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 5/10/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Insulation | 5/15/2024 | Partial Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 5/15/2024 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 5/22/2024 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 5/22/2024 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 5/22/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 5/29/2024 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 5/31/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 5/31/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 5/31/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 6/6/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Insulation | 6/6/2024 | Partial Approval | CHRISTOPHER WILSON |
| HVAC-Rough | 6/11/2024 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 6/11/2024 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/11/2024 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 6/14/2024 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 6/14/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 6/14/2024 | Conditional Approval | STEPHANIE SWANSON |
| Insulation | 6/14/2024 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 6/20/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 6/20/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 6/21/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 6/25/2024 | Approved | STEPHANIE SWANSON |
| Insulation | 6/25/2024 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 6/28/2024 | Approved | CHRISTOPHER WILSON |
| Green Building Final | 10/11/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 10/11/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 10/11/2024 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 10/11/2024 | SGSOV Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 10/25/2024 | Corrections Issued | STEPHANIE SWANSON |
| Final | 10/25/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 10/25/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 10/25/2024 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 10/25/2024 | SGSOV Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 11/1/2024 | Approved | CHRISTOPHER WILSON |
| Final | 11/1/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Smoke Detectors | 11/1/2024 | Approved | CHRISTOPHER WILSON |
| Final | 11/7/2024 | OK to Issue CofO | STEPHANIE SWANSON |