4250-4252 N SALTILLO ST 91364
Certificate Information: 4250-4252 N SALTILLO ST 91364
- Application / Permit
- 23014-20000-03217
- Plan Check / Job No.
- B23VN10746
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENCLOSE EXISTING COVERED PORCH AND CONVERSION OF ENTIRE 1ST FLOOR TO AN ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (e) (NO CHANGE TO BUILDING FOOTPRINT)
- Permit Issued
- Issued on 10/10/2025
- Issuing Office
- Current Status
- Issued on 10/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2023 | CARLOS MONTES |
| Corrections Issued | 9/28/2023 | CARLOS MONTES |
| Quality Review Completed | 9/28/2023 | GARO TELMI |
| Applicant returned to address corrections | 1/14/2025 | CARLOS MONTES |
| Applicant returned to address corrections | 3/11/2025 | CARLOS MONTES |
| Plan Check Approved | 10/8/2025 | CARLOS MONTES |
| Issued | 10/10/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/11/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/24/2025 | CARLOS AGUILERA |
| Specific Plan | Cleared | 7/25/2025 | JUDE HERNANDEZ |
| Specific Plan | Cleared | 7/25/2025 | JUDE HERNANDEZ |
| Grading Pre-Inspection | Cleared | 10/8/2025 | CHARLES POWELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kazemi,, Milad; Lic. No.: C92143 | 28025 DOROTHY DR STE 202 AGOURA HILLS, CA 91301 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/7/2025 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 3/2/2026 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 3/10/2026 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 4/1/2026 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 4/22/2026 | Corrections Issued | SEAN WIRCH |
| Green Building Rough | 4/22/2026 | Not Ready for Inspection | SEAN WIRCH |
| BUILDING-Rough-Frame | 5/5/2026 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 5/5/2026 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 5/5/2026 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 5/5/2026 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 5/14/2026 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 5/14/2026 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 5/14/2026 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 5/14/2026 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 5/20/2026 | Partial Approval | JOHN HAYES |
| Green Building Rough | 5/20/2026 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 5/20/2026 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 5/28/2026 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 5/28/2026 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 5/28/2026 | Not Ready for Inspection | JOHN HAYES |