7960-7962 N MAMMOTH AVE 91402
Certificate Information: 7960-7962 N MAMMOTH AVE 91402
- Application / Permit
- 23014-20000-03202
- Plan Check / Job No.
- B23VN10708
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN CONVERT (E) ATTACHED GARAGE WITH 15'-6" X 17-10" ADDITION TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e) AND CONVERT (E) CARPORT TO MAIN DWELLING.
- Permit Issued
- Issued on 11/24/2023
- Issuing Office
- Current Status
- CofO Issued on 4/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 8/18/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 11/15/2023 | ALEC MOUSAKHANIAN |
| Issued | 11/24/2023 | APPLICANT |
| CofO in Progress | 1/29/2025 | VINCENT HANLEY |
| Permit Finaled | 4/8/2025 | RUBEN SALAS |
| CofO Issued | 4/8/2025 | RUBEN SALAS |
| Permit Finaled | 4/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/29/2023 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 8/29/2023 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/10/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/17/2024 | Approved | VINCENT HANLEY |
| Pre-Inspection | 6/4/2024 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 6/18/2024 | Partial Approval | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 7/3/2024 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 7/3/2024 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/3/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 7/3/2024 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 8/14/2024 | Approved | GREGG CUMMINGS |
| Sewer | 8/14/2024 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 8/14/2024 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/16/2024 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 9/16/2024 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2024 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 9/16/2024 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/23/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 9/23/2024 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 9/23/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 9/25/2024 | Partial Approval | GREGG CUMMINGS |
| Interior/Exterior Lathing | 9/25/2024 | Partial Approval | GREGG CUMMINGS |
| Insulation | 9/27/2024 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/30/2024 | Approved | GREGG CUMMINGS |
| Insulation | 9/30/2024 | Corrections Issued | GREGG CUMMINGS |
| Drywall Nailing | 10/2/2024 | Corrections Issued | GREGG CUMMINGS |
| Drywall Nailing | 10/3/2024 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 10/3/2024 | Approved | GREGG CUMMINGS |
| Shower Pan | 10/15/2024 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2024 | Partial Approval | GREGG CUMMINGS |
| Interior/Exterior Lathing | 10/24/2024 | Partial Approval | GREGG CUMMINGS |
| Final | 12/31/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 12/31/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 12/31/2024 | Approved | JENNIFER RABUCHIN |
| Final | 1/17/2025 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Final | 1/28/2025 | Approved | VINCENT HANLEY |
| Final | 1/28/2025 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 1/28/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 1/28/2025 | Approved | VINCENT HANLEY |