24125 W ALBERS ST 91367
Certificate Information: 24125 W ALBERS ST 91367
- Application / Permit
- 23014-20000-03195
- Plan Check / Job No.
- B23VN10684
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN - Addtion to (E) SFD, interior remodel, and addition of bathroom shower fixture.
- Permit Issued
- Issued on 10/12/2023
- Issuing Office
- Current Status
- CofO Issued on 6/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2023 | HOOMAN HAJIZADEH |
| Corrections Issued | 8/29/2023 | HOOMAN HAJIZADEH |
| Quality Review Completed | 9/7/2023 | KAVIAN REFAHI |
| Applicant returned to address corrections | 10/3/2023 | HOOMAN HAJIZADEH |
| Plan Check Approved | 10/5/2023 | HOOMAN HAJIZADEH |
| Issued | 10/12/2023 | APPLICANT |
| CofO in Progress | 5/30/2024 | GEVORK IPCHYAN |
| Permit Finaled | 6/17/2024 | JOHN JANSON |
| CofO Issued | 6/17/2024 | JOHN JANSON |
| Permit Finaled | 6/17/2024 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/19/2023 | CHARLES POWELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gonzalez,, Fernando Francisco; Lic. No.: C53256 | 11607 AMESTOY AVE GRANADA HILLS, CA 91344 |
| Engineer | Gonzalez,, Fernando Francisco; Lic. No.: NA53256 | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/20/2023 | Corrections Issued | MORRIS JACKSON |
| Sewer | 11/20/2023 | Approved | MORRIS JACKSON |
| Underground Mechanical | 11/20/2023 | Approved | MORRIS JACKSON |
| Footing/Foundation/Slab | 11/30/2023 | Approved | TROY SANDERS |
| Deputy Wood Construction | 1/8/2024 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 1/9/2024 | Partial Approval | TROY SANDERS |
| Interior/Exterior Lathing | 1/17/2024 | Partial Approval | MORRIS JACKSON |
| Rough-Elec/Plmb/HVAC | 1/17/2024 | Corrections Issued | MORRIS JACKSON |
| ELECTRICAL-Rough | 1/22/2024 | Approved | MORRIS JACKSON |
| HVAC-Rough | 1/22/2024 | Approved | MORRIS JACKSON |
| Insulation | 1/22/2024 | Approved | MORRIS JACKSON |
| Shower Pan | 1/22/2024 | Approved | MORRIS JACKSON |
| Drywall Nailing | 1/26/2024 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 1/26/2024 | Approved | SEAN WIRCH |
| ELECTRICAL-Final | 4/12/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| HVAC-Final | 4/12/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| PLUMBING-Final | 4/12/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Pool/Spa Cover | 4/12/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| ELECTRICAL-Final | 4/26/2024 | Corrections Issued | GEVORK IPCHYAN |
| HVAC-Final | 4/26/2024 | Approved | GEVORK IPCHYAN |
| PLUMBING-Final | 4/26/2024 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 5/16/2024 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 5/16/2024 | Approved | GEVORK IPCHYAN |
| Final | 5/16/2024 | Partial Approval | GEVORK IPCHYAN |
| HVAC-Final | 5/16/2024 | Approved | GEVORK IPCHYAN |
| PLUMBING-Final | 5/16/2024 | Approved | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 5/16/2024 | SGSOV Approved | GEVORK IPCHYAN |
| Smoke Detectors | 5/16/2024 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 5/22/2024 | Approved | GEVORK IPCHYAN |
| Final | 5/22/2024 | Partial Approval | GEVORK IPCHYAN |
| HVAC-Final | 5/22/2024 | Approved | GEVORK IPCHYAN |
| PLUMBING-Final | 5/22/2024 | Approved | GEVORK IPCHYAN |
| Final | 5/29/2024 | OK to Issue CofO | GEVORK IPCHYAN |