7445 N RHEA AVE 91335

Certificate Information: 7445 N RHEA AVE 91335

Application / Permit
23014-20000-03177
Plan Check / Job No.
B23VN10639
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT EXISTING DETACHED GARAGE TO AN A.D.U. AND ADD TO A.D.U. PER LAMC 12.22 A.33 (c) AND (d)
Permit Issued
Issued on 12/30/2023
Issuing Office
Current Status
CofO Issued on 3/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2023 APPLICANT
Assigned to Plan Check Engineer 8/15/2023 JOHNPAUL ISIP
Corrections Issued 8/16/2023 JOHNPAUL ISIP
Plan Check Approved 12/28/2023 CAROLEAN BASMA
Issued 12/30/2023 APPLICANT
CofO in Progress 2/24/2025 ARUTYUN MADATYAN
Permit Finaled 3/10/2025 JOHN JANSON
CofO Issued 3/10/2025 JOHN JANSON
Permit Finaled 3/10/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/22/2023 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 8/22/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 8/23/2023 MEGAN GODINEZ
Sewer availability Cleared 8/23/2023 MEGAN GODINEZ
Construction near power lines Cleared 12/22/2023 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/29/2024 No Access for Inspection CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 9/4/2024 Approved JEFFREY BULL
Footing/Foundation/Slab 9/4/2024 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Approved JEFFREY BULL
Green Building Rough 9/25/2024 Not Ready for Inspection JEFFREY BULL
Interior/Exterior Lathing 10/29/2024 Partial Approval JEFFREY BULL
Insulation 11/13/2024 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 11/20/2024 Approved ARUTYUN MADATYAN
Green Building Rough 11/20/2024 Approved ARUTYUN MADATYAN
Insulation 11/20/2024 Approved ARUTYUN MADATYAN
Rough-Elec/Plmb/HVAC 11/20/2024 Approved ARUTYUN MADATYAN
Drywall Nailing 12/10/2024 Approved TROY SANDERS
Shower Pan 12/10/2024 Approved TROY SANDERS
Final 2/14/2025 Corrections Issued TROY SANDERS
Green Building Final 2/14/2025 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 2/14/2025 SGSOV Approved TROY SANDERS
Service/Power Release 2/14/2025 Approved TROY SANDERS
Smoke Detectors 2/14/2025 Approved TROY SANDERS
Final 2/24/2025 OK to Issue CofO ARUTYUN MADATYAN