4267 N DENNY AVE 91602

Certificate Information: 4267 N DENNY AVE 91602

Application / Permit
23014-20000-03169
Plan Check / Job No.
B23VN10617
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO ADU PER GCS65852.2(e)(1)(A).
Permit Issued
Issued on 5/31/2024
Issuing Office
Current Status
CofO Issued on 6/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2023 APPLICANT
Assigned to Plan Check Engineer 8/15/2023 ISIS ARGUETA
Corrections Issued 8/16/2023 ISIS ARGUETA
Applicant returned to address corrections 9/7/2023 ISIS ARGUETA
Applicant returned to address corrections 9/12/2023 DANIEL ABRAMYAN
Applicant returned to address corrections 5/3/2024 DANIEL ABRAMYAN
Plan Check Approved 5/30/2024 MOHAMMAD ESMAILI
Issued 5/31/2024 APPLICANT
CofO in Progress 6/6/2025 JAVIER RAMOS JR
Permit Finaled 6/20/2025 RUBEN SALAS
Permit Finaled 6/20/2025 RUBEN SALAS
CofO Issued 6/20/2025 RUBEN SALAS

Permit Application Clearance Information

Construction within easement Cleared 8/18/2023 TINA MIRANDA
Address approval Cleared 8/22/2023 TAL SHEMEN
Sewer availability Cleared 8/22/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 8/23/2023 TAL SHEMEN

Contact Information

Contractor Mc Kernan Inspections And Construction; Lic. No.: 935880-B       ,
Contractor Mc Kernan Inspections Inc; Lic. No.: 935880-B       ,
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/31/2024 Corrections Issued CHRISTOPHE COCHRAN
Underground Mechanical 7/31/2024 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 8/13/2024 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 8/21/2024 Approved CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 8/30/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 9/3/2024 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 9/9/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 12/19/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 12/19/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 12/19/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 12/19/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/10/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 1/10/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 1/17/2025 Partial Approval CHRISTOPHER ROJAS
Insulation 2/7/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 2/12/2025 Approved CHRISTOPHER ROJAS
Shower Pan 2/12/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 2/13/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 5/21/2025 Partial Inspection JAVIER RAMOS JR
Final 5/21/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 5/21/2025 Approved JAVIER RAMOS JR
HVAC-Final 5/21/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/21/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 5/21/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 6/5/2025 Approved JAVIER RAMOS JR
Final 6/5/2025 OK to Issue CofO JAVIER RAMOS JR
PLUMBING-Final 6/5/2025 Approved JAVIER RAMOS JR