10140 N STANWIN AVE 91331

Certificate Information: 10140 N STANWIN AVE 91331

Application / Permit
23014-20000-03141
Plan Check / Job No.
B23VN10542
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD IRR. 26'-11" X 21'-8" NEW BDRM & BTHRM AND REMODEL TO (E) SFD
Permit Issued
Issued on 8/18/2023
Issuing Office
Current Status
CofO Issued on 10/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/7/2023 APPLICANT
Assigned to Plan Check Engineer 8/11/2023 ARTIN ZARUKIAN
Corrections Issued 8/12/2023 ARTIN ZARUKIAN
Plan Check Approved 8/17/2023 ANGELICA MARTINEZ
Issued 8/18/2023 APPLICANT
CofO in Progress 4/11/2024 JENNIFER RABUCHIN
CofO Issued 10/25/2024 DANIEL ORRANTE
Permit Finaled 10/25/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/15/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 8/15/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/17/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/30/2023 Approved JENNIFER RABUCHIN
METHANE-Barrier 8/30/2023 Approved JENNIFER RABUCHIN
METHANE-Subgrade 8/30/2023 Approved JENNIFER RABUCHIN
Insulation 9/18/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 9/18/2023 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 9/25/2023 Partial Approval JENNIFER RABUCHIN
Wood Frame 9/25/2023 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/4/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 10/4/2023 Not Ready for Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 10/4/2023 Corrections Issued JENNIFER RABUCHIN
METHANE-Rough 10/4/2023 Approved JENNIFER RABUCHIN
Insulation 10/10/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 10/10/2023 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 11/8/2023 Approved KEVIN BERBERYAN
Green Building Rough 11/8/2023 Approved KEVIN BERBERYAN
ELECTRICAL-Final 1/12/2024 Approved JENNIFER RABUCHIN
HVAC-Final 1/12/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 1/12/2024 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/20/2024 Approved JENNIFER RABUCHIN
Final 2/20/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 2/20/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/20/2024 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 2/20/2024 Approved JENNIFER RABUCHIN
Final 4/10/2024 OK to Issue CofO JENNIFER RABUCHIN
PLUMBING-Final 4/10/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/10/2024 SGSOV Approved JENNIFER RABUCHIN