10140 N STANWIN AVE 91331
Certificate Information: 10140 N STANWIN AVE 91331
- Application / Permit
- 23014-20000-03141
- Plan Check / Job No.
- B23VN10542
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD IRR. 26'-11" X 21'-8" NEW BDRM & BTHRM AND REMODEL TO (E) SFD
- Permit Issued
- Issued on 8/18/2023
- Issuing Office
- Current Status
- CofO Issued on 10/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 8/12/2023 | ARTIN ZARUKIAN |
| Plan Check Approved | 8/17/2023 | ANGELICA MARTINEZ |
| Issued | 8/18/2023 | APPLICANT |
| CofO in Progress | 4/11/2024 | JENNIFER RABUCHIN |
| CofO Issued | 10/25/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/25/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/15/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/15/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/30/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Barrier | 8/30/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 8/30/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 9/18/2023 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/18/2023 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2023 | Partial Approval | JENNIFER RABUCHIN |
| Wood Frame | 9/25/2023 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/4/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 10/4/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/4/2023 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Rough | 10/4/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 10/10/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/10/2023 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 11/8/2023 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 11/8/2023 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 1/12/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 1/12/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/12/2024 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/20/2024 | Approved | JENNIFER RABUCHIN |
| Final | 2/20/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 2/20/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/20/2024 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 2/20/2024 | Approved | JENNIFER RABUCHIN |
| Final | 4/10/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| PLUMBING-Final | 4/10/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 4/10/2024 | SGSOV Approved | JENNIFER RABUCHIN |